Interconnection queue in the USA (2024 requests) — page 21

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,283285.2 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,283 requests · page 21 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 611, Maury County
Solar
100 MWIn study Maury, TNSoutheast Mar 2024target 2027
Battery storage project J3421, Huron County
Battery storage
100 MWIn study Huron, MIMISO Apr 2024target 2028
Surplus; J385
Other
100 MWIn study Chisago, MNMISO Jul 2024target 2026
Onshore wind project J3341, Vermilion County
Onshore wind
100 MWIn study Vermilion, ILMISO Apr 2024target 2028
Battery storage project J3861, Branch County
Battery storage
100 MWIn study Branch, MIMISO Dec 2024target 2028
Battery storage project J3268, Gratiot County
Battery storage
100 MWIn study Gratiot, MIMISO Apr 2024target 2027
Solar project J3470, Tuscola County
Solar
100 MWIn study Tuscola, MIMISO Apr 2024target 2027
Kce NY 34
Battery storage · KCE NY 34, LLC
100 MWIn study Ulster, NYNYISO Sep 2024target 2029
Jericho Solar
Solar · Jericho Solar Park LLC
100 MWIn study Franklin, NYNYISO Oct 2024target 2029
Battery storage project 150, Skagit County
Battery storage
100 MWIn study Skagit, WAWest Apr 2024target 2027
Solar project 5RSC-2024-04, Pueblo County
Solar
100 MWIn study Pueblo, COWest Jan 2024target 2028
Aria Storage 1
Battery storage · Terra-Gen Development Company, LLC
100 MWIn study Dutchess, NYNYISO Oct 2024target 2028
Solar project J3466, Winnebago County
Solar
100 MWIn study Winnebago, WIMISO Apr 2024target 2028
Battery storage project 643, Shelby County
Battery storage
100 MWIn study Shelby, TNSoutheast Sep 2024target 2027
Solar project 266, Hampton County
Solar
100 MWIn study Hampton, SCSoutheast Jun 2024target 2028
Battery storage project Q109, Los Angeles County
Battery storage
100 MWIn study Los Angeles, CAWest Jun 2024target 2027
Surplus; J758
Other
100 MWIn study Calhoun, MIMISO Aug 2024target 2027
Adam Bryant BESS
Battery storage · Adam Bryant BESS LLC
99.5 MWIn study Medina, TXERCOT Feb 2024target 2027
Battery storage project 956240, Rutherford County
Battery storage
99.0 MWIn study Rutherford, NCSoutheast Jun 2024
Battery storage project 956244, Robeson County
Battery storage · Duke Energy Progress, LLC.
99.0 MWIn study Robeson, NCSoutheast Jun 2024
Solar project 660, Jackson County
Solar
99.0 MWIn study Jackson, ALSoutheast Oct 2024target 2032
Replacing 95 MW of coal with BESS; Meramec 1, 2, 3, 4
Other
98.8 MWIn study St. Louis, MOMISO Dec 2024target 2025
Cannibal Draw Storage
Solar + storage · Cannibal Draw Solar, LLC
98.6 MWAgreement signed Glasscock, TXERCOT Jul 2024target 2028
Solar project 642, Muhlenberg County
Solar
96.0 MWIn study Muhlenberg, KYSoutheast Sep 2024target 2033
Solar project 609, Mccracken County
Solar
96.0 MWIn study Mccracken, KYSoutheast Feb 2024target 2027
Hemlock Hollow Wind
Onshore wind · Liberty Renewables Inc.
95.0 MWIn study Cattaraugus, NYNYISO Aug 2024target 2029
Gas project LGE-GIS-2024-006, Jefferson County
Gas
94.0 MWAgreement signed Jefferson, KYSoutheast May 2024target 2026
Anawa La Solar
Solar + storage · Anawa La Solar LLC
93.3 MWIn study Hidalgo, TXERCOT Mar 2024target 2027
Basketflower Storage
Solar + storage · Basketflower Solar, LLC
92.0 MWIn study Eastland, TXERCOT Oct 2024target 2027
Raghorn Solar SLF
Solar + storage · Raghorn Solar LLC
91.9 MWIn study Jim Wells, TXERCOT May 2024target 2027
Solar project J3777, Cheboygan County
Solar
91.8 MWIn study Cheboygan, MIMISO Apr 2024target 2028
Callan Solar
Solar · Menard PV, LLC
91.0 MWIn study Menard, TXERCOT Jun 2024target 2028
Wild Horse Desert Storage
Solar + storage · Wild Horse Desert Solar, LLC
90.3 MWIn study Dimmit, TXERCOT Dec 2024target 2028
Hell Gate Energy Storage
Battery storage · the NY Power Authority
90.0 MWIn study Bronx, NYNYISO Oct 2024target 2028
Solar project J3953, Faulkner County
Solar
90.0 MWIn study Faulkner, ARMISO Nov 2024target 2028
Gas project 958348, Person County
Gas · Duke Energy Progress, LLC
89.0 MWIn study Person, NCSoutheast Jun 2024
Gas project J3870, Vigo County
Gas
87.0 MWIn study Vigo, INMISO Dec 2024target 2002
Surplus; J1224/J1329
Other
85.1 MWIn study Washtenaw, MIMISO Oct 2024target 2028
Solar project J3914, Jefferson Davis Parish County
Solar
85.0 MWIn study Jefferson Davis Parish, LAMISO Oct 2024target 2030
Solar project J3988, Morehouse Parish County
Solar
85.0 MWIn study Morehouse Parish, LAMISO Oct 2024target 2030
Billie Storage
Battery storage · Weslaco Storage LLC
83.8 MWIn study Hidalgo, TXERCOT Jul 2024target 2029
M-Bar BESS I
Solar + storage · M-Bar Energy I, LLC
82.1 MWIn study Ector, TXERCOT Dec 2024target 2028
Juniperusss
Solar + storage · BLUE STONE RENEWABLE XXI LLC
80.3 MWIn study Hopkins, TXERCOT Jan 2024target 2029
Solar project J3653, Washtenaw County
Solar
80.0 MWIn study Washtenaw, MIMISO Apr 2024target 2028
Solar project 963468, Wilson County
Solar
80.0 MWIn study Wilson, NCSoutheast Sep 2024
Solar project 962635, Chesterfield County
Solar · Duke Energy Progress LLC
80.0 MWIn study Chesterfield, SCSoutheast Sep 2024
Solar project 962748, Jones County
Solar
80.0 MWIn study Jones, NCSoutheast Oct 2024
Solar + storage project GEN-2024-007, Stafford County
Solar + storage
80.0 MWIn study Stafford, KSSPP Apr 2024target 2028
Surplus; Old Gold
Other
80.0 MWIn study Worth, IAMISO Jun 2024target 2029
Solar project IC-1224, Baldwin County
Solar
80.0 MWAgreement signed Baldwin, ALSoutheast Jan 2024target 2028
Page 21 of 26

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)