United States › Grid › Interconnection queues › South Carolina
SOLAR · SOUTHEASTSolar project 962635, Chesterfield County
Solar project 962635, Chesterfield County is a 80.0 MW solar request in interconnection study in the Southeast interconnection queue, in Chesterfield County, South Carolina, connecting to Duke Energy Progress.
- PlanningQueued Sep 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 962635
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Progress
- Developer
- Duke Energy Progress LLC
- Connection point (POI)
- Darlington County Plant - Florence 230 kV
- Location
- Chesterfield County, South Carolina
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Phase 2 Cluster Study - In Progress
- Queue status
- Active
- Entered queue
- 25 September 2024
Location
Marker shows the centre of Chesterfield County; the queue data does not give exact sites.
Power plants in South Carolina · Transmission lines in South Carolina
Other requests in Chesterfield County
- Solar project 566488, Chesterfield CountySolar · 74.9 MW · under construction
- Solar project PP00003, Chesterfield CountySolar · 74.9 MW · under construction
- Solar project 977873, Chesterfield CountySolar · 74.9 MW · in study
- Solar project 961214, Chesterfield CountySolar · 48.0 MW · in study
- Other project PP00052, Chesterfield CountyOther · 48.0 MW · in study
- Solar project 63, Chesterfield CountySolar · 75.0 MW · built
- Solar project 956283, Chesterfield CountySolar · 110 MW · withdrawn
- Solar project 202, Chesterfield CountySolar · 75.0 MW · withdrawn
- Solar project 915761, Chesterfield CountySolar · 74.9 MW · withdrawn
- Solar + storage project 236, Chesterfield CountySolar + storage · 74.9 MW · withdrawn
- Solar project 956721, Chesterfield CountySolar · 74.9 MW · withdrawn
- Solar project 918047, Chesterfield CountySolar · 74.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem