Requests shown1,473226.5 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,473 requests ยท page 20 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Blooming Grove Solar Energy Center
Battery storage ยท Blooming Grove Solar Energy Center LLC
50.0 MWWithdrawn / abandoned Mclean, ILPJM Mar 2019target 2022
Solar project GEN-2019-010, Cass County
Solar
50.0 MWWithdrawn / abandoned Cass, NESPP Apr 2019target 2022
Battery storage project 1116, Uinta County
Battery storage
50.0 MWWithdrawn / abandoned Uinta, WYWest Feb 2019target 2022
Solar project AF1-270, Logan County
Solar ยท Fountain Point Solar Energy LLC
50.0 MWWithdrawn / abandoned Logan, OHPJM Sep 2019target 2022
Solar project IC-778, Dodge County
Solar
50.0 MWWithdrawn / abandoned Dodge, GASoutheast Feb 2019
Solar + storage project AF1-067, Caroline County
Solar + storage
50.0 MWWithdrawn / abandoned Caroline, VAPJM Aug 2019target 2022
Solar project AF1-332, Lee County
Solar
50.0 MWWithdrawn / abandoned Lee, ILPJM Sep 2019target 2023
Appleseed Energy Storage
Battery storage ยท esVolta, LP
50.0 MWWithdrawn / abandoned Greene, NYNYISO Feb 2019
Battery storage project GI-2019-4, Pueblo County
Battery storage
50.0 MWWithdrawn / abandoned Pueblo, COWest Mar 2019target 2022
Solar project AF1-152, Pasquotank County
Solar ยท Otter Creek Wind Farm, LLC d/b/a Aurora Solar LLC
50.0 MWWithdrawn / abandoned Pasquotank, NCPJM Sep 2019target 2023
Battery storage project IA-PNM-2019-22, Santa Fe County
Battery storage
50.0 MWWithdrawn / abandoned Santa Fe, NMWest Apr 2019target 2021
Battery storage project J1236, St. Landry Parish County
Battery storage
50.0 MWWithdrawn / abandoned St. Landry Parish, LAMISO Apr 2019target 2022
Other project AF2-015
Other
50.0 MWWithdrawn / abandoned PJM Oct 2019target 2019
Battery storage project AE2-170, Delaware County
Battery storage
50.0 MWWithdrawn / abandoned Delaware, INPJM Mar 2019target 2022
Solar project AE2-320, Pickaway County
Solar
50.0 MWWithdrawn / abandoned Pickaway, OHPJM Mar 2019target 2022
Battery storage project J1259, Pike County
Battery storage
50.0 MWWithdrawn / abandoned Pike, MSMISO Apr 2019target 2022
Solar project GEN-2019-050, Gove County
Solar
50.0 MWWithdrawn / abandoned Gove, KSSPP May 2019target 2023
Gas project J1370, Chippewa County
Gas
50.0 MWWithdrawn / abandoned Chippewa, MIMISO Apr 2019target 2021
Battery storage project J1238, Rapides Parish County
Battery storage
50.0 MWWithdrawn / abandoned Rapides Parish, LAMISO Apr 2019target 2022
Solar + storage project GI-2019-7, Pueblo County
Solar + storage
50.0 MWWithdrawn / abandoned Pueblo, COWest Jul 2019
Battery storage project AF2-022, Cumberland County
Battery storage
50.0 MWWithdrawn / abandoned Cumberland, NJPJM Nov 2019target 2021
Battery storage project Company 175, Clark County
Battery storage
50.0 MWWithdrawn / abandoned Clark, NVWest Mar 2019target 2023
Battery storage project GEN-2019-024, Wibaux County
Battery storage
50.0 MWWithdrawn / abandoned Wibaux, MTSPP May 2019target 2023
Solar project 575, Union County
Solar
50.0 MWWithdrawn / abandoned Union, ORWest Dec 2019
Solar project AE2-073, Licking County
Solar
50.0 MWWithdrawn / abandoned Licking, OHPJM Feb 2019target 2021
Chaparrel Storage
Battery storage
50.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2019target 2023
Battery storage project GEN-2019-048, Jackson County
Battery storage
50.0 MWWithdrawn / abandoned Jackson, MOSPP May 2019target 2027
Battery storage project J1285, Linn County
Battery storage
50.0 MWWithdrawn / abandoned Linn, IAMISO Apr 2019target 2023
Glenwood Power Station Battery Energy Storage System
Battery storage ยท National Grid Generation LLC
50.0 MWWithdrawn / abandoned Nassau, NYNYISO Nov 2019
Battery storage project Company JW1, Washoe County
Battery storage
50.0 MWWithdrawn / abandoned Washoe, NVWest Mar 2019target 2023
McAdoo Solar
Solar + storage
50.0 MWWithdrawn / abandoned Schuylkill, PAPJM Feb 2019target 2025
Solar project J1433, Washington Parish County
Solar
50.0 MWWithdrawn / abandoned Washington Parish, LAMISO Apr 2019target 2021
Battery storage project J1245, Arkansas County
Battery storage
50.0 MWWithdrawn / abandoned Arkansas, ARMISO Apr 2019target 2022
Line Creek Solar
Solar ยท sPower Development Company, LLC
50.0 MWWithdrawn / abandoned Schoharie, NYNYISO Oct 2019
Brazos BESS 2
Other ยท Brazos Wind Ventures, LLC
50.0 MWWithdrawn / abandoned Borden, TXERCOT Aug 2019target 2022
Intrepid Storage 69
Battery storage ยท Hecate Grid Intrepid 1 LLC
50.0 MWWithdrawn / abandoned Nassau, NYNYISO Oct 2019
Battery storage project AF1-066, Loudoun County
Battery storage
50.0 MWWithdrawn / abandoned Loudoun, VAPJM Aug 2019target 2021
Solar project GEN-2019-070, Madison County
Solar
50.0 MWWithdrawn / abandoned Madison, NESPP May 2019target 2027
Gas project J1206, Branch County
Gas
50.0 MWWithdrawn / abandoned Branch, MIMISO Apr 2019target 2021
Battery storage project GEN-2019-066, Beckham County
Battery storage
50.0 MWWithdrawn / abandoned Beckham, OKSPP May 2019target 2026
Battery storage project GEN-2019-013, Roger Mills County
Battery storage
50.0 MWWithdrawn / abandoned Roger Mills, OKSPP Apr 2019target 2026
Old 300 Storage
Other ยท Old 300 Solar Center, LLC
50.0 MWWithdrawn / abandoned Fort Bend, TXERCOT Nov 2019target 2021
Battery storage project GEN-2019-038, Potter County
Battery storage
50.0 MWWithdrawn / abandoned Potter, TXSPP May 2019target 2021
Solar project J1287, Tunica County
Solar
50.0 MWWithdrawn / abandoned Tunica, MSMISO Apr 2019target 2022
Gas project J1207, Branch County
Gas
50.0 MWWithdrawn / abandoned Branch, MIMISO Apr 2019target 2021
Cardinal Solar
Solar
49.9 MWWithdrawn / abandoned Union, OHPJM Mar 2019target 2023
Solar project AE2-302, Jackson County
Solar
49.9 MWWithdrawn / abandoned Jackson, OHPJM Mar 2019target 2022
Solar project AF1-230, Crawford County
Solar
49.0 MWWithdrawn / abandoned Crawford, OHPJM Sep 2019target 2022
Solar project J1344, Mills County
Solar
48.0 MWWithdrawn / abandoned Mills, IAMISO Apr 2019target 2022
Solar project J1420, Rock Island County
Solar
48.0 MWWithdrawn / abandoned Rock Island, ILMISO Apr 2019target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)