United States βΊ Grid βΊ Interconnection queues βΊ Kansas
SOLAR Β· SPPSolar project GEN-2019-050, Gove County
Solar project GEN-2019-050, Gove County is a 50.0 MW solar request withdrawn in the SPP interconnection queue, in Gove County, Kansas, connecting to SUNC.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2019 (completed)
- Withdrawn / abandonedApr 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2019-050
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Grinnell 115kV
- Location
- Gove County, Kansas
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 24 May 2019
- Proposed online date
- June 2023
- Withdrawn
- April 2022
Location
Marker shows the centre of Gove County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem