GAS Β· MISO

Gas project J1370, Chippewa County

Gas project J1370, Chippewa County is a 50.0 MW gas request withdrawn in the MISO interconnection queue, in Chippewa County, Michigan, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1370
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
9 Mile SW STA - Dafter 69kV Line
Location
Chippewa County, Michigan
Technology
Gas: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
29 April 2019
Proposed online date
March 2021
Withdrawn
March 2022

Location

Marker shows the centre of Chippewa County; the queue data does not give exact sites.