United States βΊ Grid βΊ Interconnection queues βΊ Michigan
ONSHORE WIND Β· MISOOnshore wind project J119, Chippewa County
Onshore wind project J119, Chippewa County is a 61.2 MW onshore wind request withdrawn in the MISO interconnection queue, in Chippewa County, Michigan.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2010 (completed)
- Withdrawn / abandonedSep 2012 (project stopped here)
- ConsentedSep 2012 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J119
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Pine River 69 kV Substation
- Location
- Chippewa County, Michigan
- Technology
- Wind: 61.2 MW
- Total requested
- 61.2 MW
- Study phase
- DPP - SIS
- Queue status
- Withdrawn
- Entered queue
- 17 March 2010
- Agreement signed
- 13 September 2012
- Proposed online date
- June 2011
- Withdrawn
- September 2012
Location
Marker shows the centre of Chippewa County; the queue data does not give exact sites.