πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project J119, Chippewa County

Onshore wind project J119, Chippewa County is a 61.2 MW onshore wind request withdrawn in the MISO interconnection queue, in Chippewa County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2010 (completed)
  2. Withdrawn / abandonedSep 2012 (project stopped here)
  3. ConsentedSep 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J119
Grid region
MISO (Midcontinent)
Connection point (POI)
Pine River 69 kV Substation
Location
Chippewa County, Michigan
Technology
Wind: 61.2 MW
Total requested
61.2 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
17 March 2010
Agreement signed
13 September 2012
Proposed online date
June 2011
Withdrawn
September 2012

Location

Marker shows the centre of Chippewa County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Chippewa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem