United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project AE2-302, Jackson County
Solar project AE2-302, Jackson County is a 49.9 MW solar request withdrawn in the PJM interconnection queue, in Jackson County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2019 (completed)
- Withdrawn / abandonedOct 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AE2-302
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- East Beaver-Lick 138 kV
- Location
- Jackson County, Ohio
- Technology
- Solar: 49.9 MW
- Total requested
- 49.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 29 March 2019
- Proposed online date
- July 2022
- Withdrawn
- October 2023
Location
Marker shows the centre of Jackson County; the queue data does not give exact sites.
Other requests in Jackson County
- Dixon SolarSolar Β· 70.0 MW Β· agreement signed
- Dixon SolarSolar Β· 70.0 MW Β· agreement signed
- Solar project AH1-055, Jackson CountySolar Β· 220 MW Β· in study
- Solar + storage project AI1-074, Jackson CountySolar + storage Β· 120 MW Β· in study
- Solar + storage project AG2-548, Jackson CountySolar + storage Β· 80.0 MW Β· in study
- Solar + storage project AG2-665, Jackson CountySolar + storage Β· 80.0 MW Β· in study
- Battery storage project AH1-554, Jackson CountyBattery storage Β· 150 MW Β· withdrawn
- Solar + storage project AG1-380, Jackson CountySolar + storage Β· 90.0 MW Β· withdrawn
- Solar project AC2-046, Jackson CountySolar Β· 63.0 MW Β· withdrawn
- Solar project AC2-035, Jackson CountySolar Β· 49.0 MW Β· withdrawn
- Solar project AC2-037, Jackson CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem