Requests shown575,942 MW
Active in queue5,942 MW57 requests
Agreement signed1,462 MW14 requests
Withdrawn40746.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

57 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH2-071, Wicomico County
Solar
2.0 MWIn study Wicomico, MDPJM Jan 2022target 2023
Solar project AH2-070, Wicomico County
Solar
2.0 MWIn study Wicomico, MDPJM Jan 2022target 2023
Solar project AH2-052, Allegany County
Solar
2.0 MWIn study Allegany, MDPJM Dec 2021target 2022
Solar project AH2-053, Wicomico County
Solar
2.0 MWIn study Wicomico, MDPJM Dec 2021target 2022
Solar project AH2-054, Wicomico County
Solar
2.0 MWIn study Wicomico, MDPJM Dec 2021target 2022
Solar project AH2-065, Prince George's County
Solar
2.0 MWIn study Prince George's, MDPJM Dec 2021target 2022
Solar project AH2-055
Solar
1.0 MWIn study MDPJM Dec 2021target 2022
Page 2 of 2

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20152025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)