Withdrawn queue requests in the USA (2020 requests) — page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests · page 13 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Barrel Summit Storage
Other · KCE TX 14, LLC
117 MWWithdrawn / abandoned Ellis, TXERCOT Jun 2020target 2022
Onshore wind project G0653, Clatsop County
Onshore wind
117 MWWithdrawn / abandoned Clatsop, ORWest Jul 2020target 2024
Battery Storage
Battery storage
112 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Battery Storage
Battery storage
112 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2020target 2024
Solar project AF2-188, White County
Solar
112 MWWithdrawn / abandoned White, INPJM Mar 2020target 2023
Rutland Center Solar
Solar · Rutland Center Solar 1, LLC
110 MWWithdrawn / abandoned Jefferson, NYNYISO Aug 2020
Solar project AF2-191, St. Joseph County
Solar
110 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2020target 2023
Thousand Island Solar
Solar · Cypress Creek Renewables, LLC
110 MWWithdrawn / abandoned Jefferson, NYNYISO Oct 2020
Solar + storage project AF2-204, Grant County
Solar + storage
110 MWWithdrawn / abandoned Grant, INPJM Mar 2020target 2023
Solar project AF2-090, Hardin County
Solar
110 MWWithdrawn / abandoned Hardin, KYPJM Feb 2020target 2022
Solar project AG1-061, Sussex County
Solar · Deere Acres Solar LLC
109 MWWithdrawn / abandoned Sussex, DEPJM Jul 2020target 2021
Onshore wind project GEN-2020-019, Tripp County
Onshore wind
108 MWWithdrawn / abandoned Tripp, SDSPP Apr 2020target 2027
Finneywood Solar
Solar · Virginia Electric and Power Company
107 MWWithdrawn / abandoned Mecklenburg, VAPJM Aug 2020target 2024
Bangor Solar
Solar · SWEB Development USA, LLC
107 MWWithdrawn / abandoned Franklin, NYNYISO Oct 2020
Solar project AG1-048, Amelia County
Solar
106 MWWithdrawn / abandoned Amelia, VAPJM Jul 2020target 2022
Onshore wind project AG1-509, Grayson County
Onshore wind
105 MWWithdrawn / abandoned Grayson, VAPJM Sep 2020target 2025
Solar project AG2-018, Morgan County
Solar
105 MWWithdrawn / abandoned Morgan, OHPJM Oct 2020target 2022
Solar project LGE-GIS-2020-002, Mercer County
Solar
105 MWWithdrawn / abandoned Mercer, KYSoutheast Nov 2020target 2024
Solar project GEN-2020-089, Allen County
Solar
104 MWWithdrawn / abandoned Allen, KSSPP Apr 2020target 2026
Solar project GEN-2020-015, Johnston County
Solar
104 MWWithdrawn / abandoned Johnston, OKSPP Apr 2020target 2026
Hinton Energy Storage
Battery storage
103 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2024
Equinox Storage
Battery storage · Invenergy Storage Development LLC
103 MWWithdrawn / abandoned ERCOT Jun 2020target 2029
Cone Mountain Batt
Other · Ramsay Draw LLC
103 MWWithdrawn / abandoned Brewster, TXERCOT Sep 2020target 2021
North Bay Energy Storage
Battery storage
103 MWWithdrawn / abandoned Sonoma, CACAISO Apr 2020target 2027
Maya
Battery storage
103 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2020target 2023
Estonian 2 Solar
Solar · 249RD 8ME
102 MWWithdrawn / abandoned ERCOT Aug 2020target 2022
Aqueduct Energy Storage
Battery storage
102 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2020target 2026
Battery Storage
Battery storage
102 MWWithdrawn / abandoned Kennebec, MEISO-NE Nov 2020target 2023
Origin Energy Storage
Battery storage
102 MWWithdrawn / abandoned Shasta, CACAISO Apr 2020target 2023
Trailways Energy Storage
Battery storage
102 MWWithdrawn / abandoned Butte, CACAISO Apr 2020target 2023
Meadows Energy Storage
Battery storage
102 MWWithdrawn / abandoned Placer, CACAISO Apr 2020target 2025
Black Bear Energy Storage 1
Battery storage
102 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2023
Black Bear Energy Storage 2
Battery storage
102 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2023
Duck Pilot Storage
Battery storage
102 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2024
Coastwood Energy Storage
Battery storage
102 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2023
Viking Energy Storage
Battery storage
102 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2024
Battery storage project AF2-208, Cecil County
Battery storage
101 MWWithdrawn / abandoned Cecil, MDPJM Mar 2020target 2022
Battery storage project AF2-197, Bradford County
Battery storage
101 MWWithdrawn / abandoned Bradford, PAPJM Mar 2020target 2022
Vorsavio Grid BESS
Other · Vorsavio Grid, LLC
101 MWWithdrawn / abandoned Webb, TXERCOT Oct 2020target 2024
Beachwood Energy Storage (Mark One BESS)
Other · Mark One Energy Storage, LLC
101 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2020target 2024
Battery storage project 80, Pierce County
Battery storage
100 MWWithdrawn / abandoned Pierce, WAWest Feb 2020target 2023
Battery storage project AG1-404, Mclean County
Battery storage · Wapella Bluffs Wind Project, LLC
100 MWWithdrawn / abandoned Mclean, ILPJM Sep 2020target 2024
Solar project AG1-042, Franklin County
Solar
100 MWWithdrawn / abandoned Franklin, OHPJM Jun 2020target 2023
Solar project J1509, Leflore County
Solar
100 MWWithdrawn / abandoned Leflore, MSMISO Jun 2020target 2026
Solar + storage project 437, Lawrence County
Solar + storage
100 MWWithdrawn / abandoned Lawrence, ALSoutheast Jun 2020
Solar project AG1-437, Bertie County
Solar · RWE Solar Development, LLC
100 MWWithdrawn / abandoned Bertie, NCPJM Sep 2020target 2023
Battery storage project AG1-314, Smyth County
Battery storage
100 MWWithdrawn / abandoned Smyth, VAPJM Sep 2020target 2024
Fort Edward Solar Farm (NY53)
Solar · Fort Edward Solar LLC
100 MWWithdrawn / abandoned Washington, NYNYISO Jun 2020
Solar + storage project 447, Lowndes County
Solar + storage
100 MWWithdrawn / abandoned Lowndes, MSSoutheast Jul 2020
Solar project J1516, St. Clair County
Solar
100 MWWithdrawn / abandoned St. Clair, MIMISO Jun 2020target 2026
Page 13 of 36

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)