United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project AG1-042, Franklin County
Solar project AG1-042, Franklin County is a 100 MW solar request withdrawn in the PJM interconnection queue, in Franklin County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedAug 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-042
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Hayden 345 kV
- Location
- Franklin County, Ohio
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 26 June 2020
- Proposed online date
- December 2023
- Withdrawn
- August 2021
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Other requests in Franklin County
- Pleasant Prairie Solar Energy CenterSolar Β· 200 MW Β· agreement signed
- Pleasant Prairie Solar Energy CenterSolar Β· 50.0 MW Β· agreement signed
- Columbus FloodwallOther Β· 7.5 MW Β· built
- Battery storage project AG2-376, Franklin CountyBattery storage Β· 400 MW Β· withdrawn
- Hayden RunSolar Β· 100 MW Β· withdrawn
- Solar project AH1-270, Franklin CountySolar Β· 85.0 MW Β· withdrawn
- Solar project AB1-136, Franklin CountySolar Β· 80.0 MW Β· withdrawn
- Battery storage project AH1-318, Franklin CountyBattery storage Β· 60.0 MW Β· withdrawn
- Battery storage project AG2-499, Franklin CountyBattery storage Β· 50.0 MW Β· withdrawn
- Battery storage project AG2-498, Franklin CountyBattery storage Β· 50.0 MW Β· withdrawn
- Gas project AA1-130, Franklin CountyGas Β· 5.0 MW Β· withdrawn
- Battery storage project Z1-064, Franklin CountyBattery storage Β· 4.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem