Onshore wind project G0653, Clatsop County

Onshore wind project G0653, Clatsop County is a 117 MW onshore wind request withdrawn in the West interconnection queue, in Clatsop County, Oregon.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0653
Grid region
West (non-ISO utilities)
Connection point (POI)
A new 230 kV interconnection point onto BPA's existing 230 kV Allston - Clatsop transmission line at BPA pole #7102-23-1 or a new 230 kV interconnection point onto BPA's existing 230 kV system at BPA'
Location
Clatsop County, Oregon
Technology
Wind: 117 MW
Total requested
117 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
10 July 2020
Proposed online date
December 2024

Location

Marker shows the centre of Clatsop County; the queue data does not give exact sites.

Power plants in Oregon Β· Transmission lines in Oregon

Other requests in Clatsop County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem