United States βΊ Grid βΊ Interconnection queues βΊ Virginia
ONSHORE WIND Β· PJMOnshore wind project AG1-509, Grayson County
Onshore wind project AG1-509, Grayson County is a 105 MW onshore wind request withdrawn in the PJM interconnection queue, in Grayson County, Virginia, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedMar 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-509
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Point Lookout 69 kV
- Location
- Grayson County, Virginia
- Technology
- Wind: 105 MW
- Total requested
- 105 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 September 2020
- Proposed online date
- March 2025
- Withdrawn
- March 2022
Location
Marker shows the centre of Grayson County; the queue data does not give exact sites.
Other requests in Grayson County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem