United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2021 requests) โ€” page 12

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,149339.1 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,149 requests ยท page 12 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2022, Mower County
Solar
200 MWWithdrawn / abandoned Mower, MNMISO Oct 2021target 2024
Solar + storage project 493, Van Buren County
Solar + storage
200 MWWithdrawn / abandoned Van Buren, TNSoutheast Jul 2021
Solar project J2135, Evangeline Parish County
Solar
200 MWWithdrawn / abandoned Evangeline Parish, LAMISO Aug 2021target 2024
Battery storage project Q78, Maricopa County
Battery storage
200 MWWithdrawn / abandoned Maricopa, AZWest May 2021target 2025
Battery storage project J2199, Anoka County
Battery storage
200 MWWithdrawn / abandoned Anoka, MNMISO Aug 2021target 2024
Solar + storage project C1-06, San Juan County
Solar + storage
200 MWWithdrawn / abandoned San Juan, UTWest Apr 2021target 2024
Solar + storage project C1-09, Juab County
Solar + storage
200 MWWithdrawn / abandoned Juab, UTWest Apr 2021target 2024
Solar + storage project C1-07, San Juan County
Solar + storage
200 MWWithdrawn / abandoned San Juan, UTWest Apr 2021target 2024
Solar + storage project C1-08, Juab County
Solar + storage
200 MWWithdrawn / abandoned Juab, UTWest Apr 2021target 2024
Solar + storage project GI-2021-29, Adams County
Solar + storage
200 MWWithdrawn / abandoned Adams, COWest Oct 2021target 2024
Solar + storage project C1-55, Carbon County
Solar + storage
199 MWWithdrawn / abandoned Carbon, WYWest May 2021target 2025
Solar + storage project C1-19, Marion County
Solar + storage
199 MWWithdrawn / abandoned Marion, ORWest May 2021target 2025
Solar project GI-2021-9, Pueblo County
Solar
199 MWWithdrawn / abandoned Pueblo, COWest Apr 2021target 2024
Solar project C1-28, Iron County
Solar
199 MWWithdrawn / abandoned Iron, UTWest May 2021target 2024
Solar + storage project GI-2021-14, Adams County
Solar + storage
199 MWWithdrawn / abandoned Adams, COWest Sep 2021target 2025
Solar + storage project C1-17, Box Elder County
Solar + storage
199 MWWithdrawn / abandoned Box Elder, UTWest May 2021target 2025
Battery storage project GI-2021-16, Arapahoe County
Battery storage
199 MWWithdrawn / abandoned Arapahoe, COWest Sep 2021target 2025
Solar + storage project C1-21, Caribou County
Solar + storage
199 MWWithdrawn / abandoned Caribou, IDWest May 2021target 2025
Solar + storage project IA-PNM-2021-21, Santa Fe County
Solar + storage
199 MWWithdrawn / abandoned Santa Fe, NMWest Oct 2021target 2024
Solar project J2167, Calcasieu Parish County
Solar
198 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Nov 2021target 2023
Cherryblossom Hybrid Solar
Solar + storage
197 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2024
Gas project J2144, Jasper County
Gas
195 MWWithdrawn / abandoned Jasper, INMISO Sep 2021target 2024
Onshore wind project C1-53, Albany County
Onshore wind
190 MWWithdrawn / abandoned Albany, WYWest May 2021target 2024
Solar project J2018, Clark County
Solar
190 MWWithdrawn / abandoned Clark, WIMISO Nov 2021target 2026
Solar + storage project 112, Lincoln County
Solar + storage
190 MWWithdrawn / abandoned Lincoln, WAWest Jan 2021target 2024
Onshore wind project J1961, Cass County
Onshore wind
190 MWWithdrawn / abandoned Cass, NDMISO Aug 2021target 2026
Battery Storage
Battery storage
189 MWWithdrawn / abandoned Plymouth, MAISO-NE Mar 2021target 2027
Battery Storage
Battery storage
189 MWWithdrawn / abandoned Plymouth, MAISO-NE Mar 2021target 2027
Gas project 82, Hillsborough County
Gas
186 MWWithdrawn / abandoned Hillsborough, FLSoutheast Nov 2021target 2023
Solar project AH1-291, Huntington County
Solar ยท Invenergy Solar Project Development LLC
185 MWWithdrawn / abandoned Huntington, INPJM Sep 2021target 2025
Solar project 96, Apache County
Solar
185 MWWithdrawn / abandoned Apache, AZWest Jun 2021target 2023
Solar + storage project GI-2021-26, Morgan County
Solar + storage
184 MWWithdrawn / abandoned Morgan, COWest Oct 2021target 2024
Solar + storage project GI-2021-24, Pueblo County
Solar + storage
184 MWWithdrawn / abandoned Pueblo, COWest Oct 2021target 2023
Flatland Solar Project
Solar ยท Flatland Solar Project, LLC
182 MWWithdrawn / abandoned ERCOT May 2021target 2025
CountySeat
Gas ยท LCRA
181 MWWithdrawn / abandoned Bastrop, TXERCOT Nov 2021target 2026
Battery storage project Q435, Maricopa County
Battery storage
180 MWWithdrawn / abandoned Maricopa, AZWest Sep 2021target 2025
Solar project AG2-576, Dekalb County
Solar
180 MWWithdrawn / abandoned Dekalb, INPJM Mar 2021target 2024
Solar + storage project GI-2021-27, Arapahoe County
Solar + storage
180 MWWithdrawn / abandoned Arapahoe, COWest Oct 2021target 2024
Solar + storage project 474, Obion County
Solar + storage
180 MWWithdrawn / abandoned Obion, TNSoutheast Apr 2021
Solar project AH1-549, Allen County
Solar ยท Leeward Renewable Energy Development, LLC
180 MWWithdrawn / abandoned Allen, INPJM Sep 2021target 2025
Onshore wind project Company LS, Lyon County
Onshore wind
180 MWWithdrawn / abandoned Lyon, NVWest Sep 2021target 2024
Solar + storage project IC-978, Sumter County
Solar + storage
180 MWWithdrawn / abandoned Sumter, GASoutheast Aug 2021
MexiAlta
Solar ยท Greenfields Solar LLC
180 MWWithdrawn / abandoned Limestone, TXERCOT Jun 2021target 2023
Solar project AH1-451
Solar
180 MWWithdrawn / abandoned WVPJM Sep 2021target 2025
Solar project AH1-016, Hardin County
Solar
180 MWWithdrawn / abandoned Hardin, KYPJM Apr 2021target 2024
Solar + storage project AH1-448, Carbon County
Solar + storage
180 MWWithdrawn / abandoned Carbon, PAPJM Sep 2021target 2024
Clarion Solar
Solar ยท IBV Energy Partners LLC
180 MWWithdrawn / abandoned Medina, TXERCOT Feb 2021target 2024
Onshore wind project J1952, Cerro Gordo County
Onshore wind
180 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2021target 2024
Solar + storage project GEN-2021-084, Kearny County
Solar + storage
180 MWWithdrawn / abandoned Kearny, KSSPP Apr 2021target 2028
Solar project J1995, Richland Parish County
Solar
180 MWWithdrawn / abandoned Richland Parish, LAMISO Aug 2021target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)