United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR Β· PJMSolar project AG2-576, Dekalb County
Solar project AG2-576, Dekalb County is a 180 MW solar request withdrawn in the PJM interconnection queue, in Dekalb County, Indiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2021 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG2-576
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Varner 345 kV
- Location
- Dekalb County, Indiana
- Technology
- Solar: 180 MW
- Total requested
- 180 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2021
- Proposed online date
- December 2024
- Withdrawn
- December 2024
Location
Marker shows the centre of Dekalb County; the queue data does not give exact sites.
Other requests in Dekalb County
- Sculpin SolarSolar Β· 180 MW Β· agreement signed
- Solar project AI2-421, Dekalb CountySolar Β· 43.2 MW Β· in study
- Solar project AI2-430, Dekalb CountySolar Β· 11.0 MW Β· in study
- Onshore wind project X1-040, Dekalb CountyOnshore wind Β· 360 MW Β· withdrawn
- Thalassa Energy ProjectSolar Β· 96.0 MW Β· withdrawn
- Solar project AF2-125, Dekalb CountySolar Β· 54.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem