Solar project J2022, Mower County

Solar project J2022, Mower County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Mower County, Minnesota, connecting to GREAT RIVER ENERGY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2021 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2022
Grid region
MISO (Midcontinent)
Utility / transmission owner
GREAT RIVER ENERGY
Connection point (POI)
Pleasant Valley 345 kV Substation
Location
Mower County, Minnesota
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
18 October 2021
Proposed online date
September 2024
Withdrawn
October 2025

Location

Marker shows the centre of Mower County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Mower County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem