Interconnection queue in the USA (2024 requests) โ€” page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,283285.2 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,283 requests ยท page 11 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Goldhill Energy Storage
Battery storage ยท Goldhill Energy Storage LLC
201 MWIn study Victoria, TXERCOT Apr 2024target 2028
Onshore wind project J3391, Coles County
Onshore wind
200 MWIn study Coles, ILMISO Apr 2024target 2027
Solar project 957146, Newberry County
Solar
200 MWIn study Newberry, SCSoutheast Jun 2024
Gemma Energy Storage
Battery storage ยท Hanwha Q CELLS USA Corp.
200 MWIn study Steuben, NYNYISO Aug 2024target 2027
Battery Storage
Battery storage
200 MWIn study Essex, MAISO-NE Jun 2024target 2028
Solar project J3477, Carroll County
Solar
200 MWIn study Carroll, IAMISO Apr 2024target 2028
Solar project J3718, Greene County
Solar
200 MWIn study Greene, ILMISO Mar 2024target 2028
Solar project IC-1266, Bullock County
Solar
200 MWAgreement signed Bullock, ALSoutheast Mar 2024target 2027
Onshore wind project J1590, Plymouth County
Onshore wind
200 MWIn study Plymouth, IAMISO Jun 2024target 2026
Battery storage project J3291, Lagrange County
Battery storage
200 MWIn study Lagrange, INMISO Apr 2024target 2028
Onshore wind project GEN-2024-058, Nowata County
Onshore wind
200 MWIn study Nowata, OKSPP Oct 2024target 2028
Solar + storage project 173, Greenlee County
Solar + storage
200 MWIn study Greenlee, AZWest Jun 2024target 2028
Solar project J3449, Pope County
Solar
200 MWIn study Pope, ARMISO Mar 2024target 2028
Battery storage project 5RSC-2024-12, Pueblo County
Battery storage
200 MWIn study Pueblo, COWest Jan 2024target 2027
Other project Q554, Pinal County
Other
200 MWIn study Pinal, AZWest May 2024target 2030
Battery storage project J3296, Hamilton County
Battery storage
200 MWIn study Hamilton, ILMISO Apr 2024target 2027
Battery storage project IC-1272, Paulding County
Battery storage
200 MWIn study Paulding, GASoutheast Mar 2024target 2030
Battery storage project GEN-2024-SR11, Garfield County
Battery storage
200 MWAgreement signed Garfield, OKSPP May 20242025
Solar project J3601, Morehouse Parish County
Solar
200 MWIn study Morehouse Parish, LAMISO Apr 2024target 2028
Solar project J1581, Nobles County
Solar
200 MWIn study Nobles, MNMISO Apr 2024target 2026
Battery storage project 5RSC-2024-09, Park County
Battery storage
200 MWIn study Park, COWest Jan 2024target 2027
Gas project 5RSC-2024-01, Weld County
Gas
200 MWIn study Weld, COWest Jan 2024target 2027
Battery storage project J3704, Redwood County
Battery storage
200 MWIn study Redwood, MNMISO Apr 2024target 2028
Solar project J3545, Ionia County
Solar
200 MWIn study Ionia, MIMISO Apr 2024target 2028
Other project Q568, Yuma County
Other
200 MWIn study Yuma, AZWest May 2024target 2028
Solar project J3472, Lapeer County
Solar
200 MWIn study Lapeer, MIMISO Apr 2024target 2028
Onshore wind project J3324, Palo Alto County
Onshore wind
200 MWIn study Palo Alto, IAMISO Apr 2024target 2029
Solar project J3434, Kandiyohi County
Solar
200 MWIn study Kandiyohi, MNMISO Mar 2024target 2028
Battery storage project J3551, Mahaska County
Battery storage
200 MWIn study Mahaska, IAMISO Apr 2024target 2027
Solar project GEN-2024-SR7, Beaver County
Solar
200 MWIn study Beaver, OKSPP Jan 2024target 2027
Battery storage project J3236, Chisago County
Battery storage
200 MWIn study Chisago, MNMISO Mar 2024target 2028
Solar + storage project 2024-G8, Clark County
Solar + storage
200 MWIn study Clark, NVWest Dec 2024target 2028
Battery storage project 149, Whatcom County
Battery storage
200 MWIn study Whatcom, WAWest Apr 2024target 2027
Onshore wind project J3849, Winnebago County
Onshore wind
200 MWIn study Winnebago, IAMISO Dec 2024target 2030
Battery storage project J3497, Pulaski County
Battery storage
200 MWIn study Pulaski, ILMISO Apr 2024target 2028
Solar project J3859, Branch County
Solar
200 MWIn study Branch, MIMISO Dec 2024target 2028
Feather Dalea BESS
Battery storage ยท RWE Clean Energy Development, LLC
200 MWIn study Glasscock, TXERCOT Oct 2024target 2027
Solar project J3719, Miami County
Solar
200 MWIn study Miami, INMISO Mar 2024target 2028
Solar project 5RSC-2024-23, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jan 2024target 2028
Onshore wind project J3713, Wapello County
Onshore wind
200 MWIn study Wapello, IAMISO Apr 2024target 2028
Solar project J3286, Sanilac County
Solar
200 MWIn study Sanilac, MIMISO Apr 2024target 2028
Onshore wind project J3338, Hamilton County
Onshore wind
200 MWIn study Hamilton, ILMISO Apr 2024target 2028
Battery storage project J3550, Dubois County
Battery storage
200 MWIn study Dubois, INMISO Apr 2024target 2027
Solar project J3725, Louisa County
Solar
200 MWIn study Louisa, IAMISO Apr 2024target 2028
SR Bartown frmly Jefferson
Solar
200 MWIn study Jefferson, GASoutheast Dec 2024target 2029
Battery storage project 661, Shelby County
Battery storage
200 MWIn study Shelby, TNSoutheast Oct 2024target 2026
Onshore wind project J3493, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Apr 2024target 2028
Solar project J1588, Cass County
Solar
200 MWIn study Cass, NDMISO Apr 2024target 2026
Solar project J3811, Clay County
Solar
200 MWIn study Clay, ILMISO Apr 2024target 2028
Onshore wind project J3655, Dallas County
Onshore wind
200 MWIn study Dallas, IAMISO Apr 2024target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)