| Project | Capacity | Status |
|---|---|---|
| Solar project GI-TC-2024-28, Weld County Solar |
222 MW | In study |
| Oystercatcher Solar Solar · Oystercatcher Solar, LLC |
222 MW | Agreement signed |
| Utley Solar Solar |
222 MW | Paused / redesign |
| Grayback Solar Solar · Grayback Solar, LLC |
222 MW | In study |
| Goodalta Solar Solar · GoodAlta Power Center LLC |
221 MW | In study |
| Solar project GEN-2018-131, Pierce County Solar |
221 MW | Agreement signed |
| Douie Solar Solar · Buffalo Spring Solar LLC |
221 MW | In study |
| Angel City Solar Solar · Angel City Energy Center, LLC |
221 MW | In study |
| Solar project J4051, Jefferson Davis Parish County Solar |
220 MW | In study |
| Solar project IC-908, Turner County Solar |
220 MW | Paused / redesign |
| Solar project J2554, Putnam County Solar |
220 MW | In study |
| Solar project AH1-055, Jackson County Solar · Furnace Solar, LLC |
220 MW | In study |
| Solar project J3418, Sangamon County Solar |
220 MW | In study |
| Eastern Cottontail Solar Solar |
220 MW | Agreement signed |
| Solar project J3495, Greene County Solar |
220 MW | In study |
| Solar project J2444, Van Buren County Solar |
220 MW | In study |
| Solar project J2001, Newaygo County Solar |
220 MW | In study |
| Solar project GEN-2024-257, Pratt County Solar |
220 MW | In study |
| Solar project J4050, Jefferson Davis Parish County Solar |
220 MW | In study |
| Solar project J4041, Menard County Solar |
220 MW | In study |
| Solar project J2814, Kalamazoo County Solar |
220 MW | In study |
| Sepanta Solar Solar · BREG - Belgian Renewable Energy Group |
217 MW | In study |
| Maratua Solar Solar · BDPU Solar Maratua, LLC |
217 MW | Paused / redesign |
| Solar project J2599, Redwood County Solar |
216 MW | In study |
| Walleye Solar Solar · Sandow Lakes Ranch Solar II, LLC |
215 MW | In study |
| Solar project J3457, Arkansas County Solar |
215 MW | In study |
| Solar project J2611, Alcona County Solar |
215 MW | In study |
| Solar project J3940, Isabella County Solar |
214 MW | In study |
| Puerto Del Sol 2 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Puerto Del Sol 1 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Deckerville Solar Park Project Solar · DTE Electric |
213 MW | In study |
| BumbleBee Solar Solar · BumbleBee Solar Farm LLC |
212 MW | In study |
| Grimes County Solar Solar · Grimes County Solar Project, LLC |
211 MW | Agreement signed |
| Rockridge Solar Solar · Magnolia Solar Development LLC |
211 MW | Agreement signed |
| Solar project J2811, Cerro Gordo County Solar |
210 MW | In study |
| Solar project AG2-245, Starke County Solar · STARKE CENTRAL PROJECT, LLC |
210 MW | In study |
| Solar project AG2-184, Knott County Solar · STMO bn, LLC |
210 MW | In study |
| Solar project J2553, Cerro Gordo County Solar |
210 MW | In study |
| Broomstick Solar Energy Centergy Center Solar |
210 MW | Paused / redesign |
| Alamosa Solar Solar |
210 MW | Paused / redesign |
| New Hickory Solar Solar · New Hickory Solar LLC |
209 MW | Agreement signed |
| Two Rivers Solar Solar · Two Rivers Solar, LLC |
209 MW | In study |
| Solar project J2050, Macon County Solar |
208 MW | In study |
| Pearl Moon Solar · Pearl Moon Solar, LLC |
208 MW | In study |
| Umbra (Stockyard) Solar Solar |
208 MW | Paused / redesign |
| Rockefeller Solar Solar |
208 MW | Paused / redesign |
| Erath County Solar Solar · Erath County Solar, LLC |
207 MW | Agreement signed |
| St. Gall Solar Solar · St. Gall Solar LLC |
207 MW | In study |
| Hoyte Solar Solar · Milano Solar LLC |
207 MW | Agreement signed |
| Fountain Point Solar Solar · Fountain Point Solar Energy LLC |
207 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)747 · 133.2 GW
- ERCOT (Texas)417 · 96.8 GW
- PJM (Mid-Atlantic, Midwest)730 · 59.8 GW
- Southeast (non-ISO utilities)544 · 51.6 GW
- SPP (Southwest Power Pool)193 · 37.7 GW
- West (non-ISO utilities)240 · 34.1 GW
- NYISO (New York)72 · 6,628 MW
- CAISO (California)25 · 6,355 MW
- ISO-NE (New England)27 · 1,425 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)