Solar interconnection queue in the USA — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 11 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GI-TC-2024-28, Weld County
Solar
222 MWIn study Weld, COWest May 2023target 2027
Oystercatcher Solar
Solar · Oystercatcher Solar, LLC
222 MWAgreement signed Ellis, TXERCOT May 2019target 2026
Utley Solar
Solar
222 MWPaused / redesign Freestone, TXERCOT Sep 2021target 2025
Grayback Solar
Solar · Grayback Solar, LLC
222 MWIn study Wilbarger, TXERCOT Nov 2025target 2028
Goodalta Solar
Solar · GoodAlta Power Center LLC
221 MWIn study Navarro, TXERCOT Jan 2021target 2027
Solar project GEN-2018-131, Pierce County
Solar
221 MWAgreement signed Pierce, NESPP Nov 2018target 2031
Douie Solar
Solar · Buffalo Spring Solar LLC
221 MWIn study Freestone, TXERCOT May 2023target 2028
Angel City Solar
Solar · Angel City Energy Center, LLC
221 MWIn study Goliad, TXERCOT Feb 2024target 2029
Solar project J4051, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project IC-908, Turner County
Solar
220 MWPaused / redesign Turner, GASoutheast Oct 2020target 2023
Solar project J2554, Putnam County
Solar
220 MWIn study Putnam, ILMISO Sep 2022target 2026
Solar project AH1-055, Jackson County
Solar · Furnace Solar, LLC
220 MWIn study Jackson, OHPJM Feb 2025target 2026
Solar project J3418, Sangamon County
Solar
220 MWIn study Sangamon, ILMISO Apr 2024target 2028
Eastern Cottontail Solar
Solar
220 MWAgreement signed Fairfield, OHPJM Jan 2019target 2028
Solar project J3495, Greene County
Solar
220 MWIn study Greene, INMISO Apr 2024target 2028
Solar project J2444, Van Buren County
Solar
220 MWIn study Van Buren, MIMISO Sep 2022target 2026
Solar project J2001, Newaygo County
Solar
220 MWIn study Newaygo, MIMISO Aug 2021target 2025
Solar project GEN-2024-257, Pratt County
Solar
220 MWIn study Pratt, KSSPP Mar 2025target 2029
Solar project J4050, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project J4041, Menard County
Solar
220 MWIn study Menard, ILMISO Jun 2025target 2030
Solar project J2814, Kalamazoo County
Solar
220 MWIn study Kalamazoo, MIMISO Sep 2022target 2026
Sepanta Solar
Solar · BREG - Belgian Renewable Energy Group
217 MWIn study Nolan, TXERCOT Oct 2022target 2029
Maratua Solar
Solar · BDPU Solar Maratua, LLC
217 MWPaused / redesign Grimes, TXERCOT Dec 2020target 2029
Solar project J2599, Redwood County
Solar
216 MWIn study Redwood, MNMISO Sep 2022target 2026
Walleye Solar
Solar · Sandow Lakes Ranch Solar II, LLC
215 MWIn study Milam, TXERCOT Jul 2018target 2027
Solar project J3457, Arkansas County
Solar
215 MWIn study Arkansas, ARMISO Apr 2024target 2027
Solar project J2611, Alcona County
Solar
215 MWIn study Alcona, MIMISO Sep 2022target 2028
Solar project J3940, Isabella County
Solar
214 MWIn study Isabella, MIMISO Feb 2025target 2030
Puerto Del Sol 2
Solar · PUERTO DEL SOL, LLC
214 MWIn study Cameron, TXERCOT May 2022target 2027
Puerto Del Sol 1
Solar · PUERTO DEL SOL, LLC
214 MWIn study Cameron, TXERCOT May 2022target 2026
Deckerville Solar Park Project
Solar · DTE Electric
213 MWIn study Sanilac, MIMISO Aug 2025target 2028
BumbleBee Solar
Solar · BumbleBee Solar Farm LLC
212 MWIn study Bee, TXERCOT Feb 2024target 2027
Grimes County Solar
Solar · Grimes County Solar Project, LLC
211 MWAgreement signed Grimes, TXERCOT Jan 2021target 2025
Rockridge Solar
Solar · Magnolia Solar Development LLC
211 MWAgreement signed Guadalupe, TXERCOT Apr 2022target 2027
Solar project J2811, Cerro Gordo County
Solar
210 MWIn study Cerro Gordo, IAMISO Sep 2022target 2026
Solar project AG2-245, Starke County
Solar · STARKE CENTRAL PROJECT, LLC
210 MWIn study Starke, INPJM Mar 2025target 2023
Solar project AG2-184, Knott County
Solar · STMO bn, LLC
210 MWIn study Knott, KYPJM Feb 2025target 2024
Solar project J2553, Cerro Gordo County
Solar
210 MWIn study Cerro Gordo, IAMISO Sep 2022target 2026
Broomstick Solar Energy Centergy Center
Solar
210 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Alamosa Solar
Solar
210 MWPaused / redesign Wilbarger, TXERCOT Dec 2020target 2025
New Hickory Solar
Solar · New Hickory Solar LLC
209 MWAgreement signed Jackson, TXERCOT Jan 2019target 2026
Two Rivers Solar
Solar · Two Rivers Solar, LLC
209 MWIn study Milam, TXERCOT Jul 2021target 2029
Solar project J2050, Macon County
Solar
208 MWIn study Macon, MOMISO Mar 2022target 2024
Pearl Moon
Solar · Pearl Moon Solar, LLC
208 MWIn study Colorado, TXERCOT Sep 2023target 2029
Umbra (Stockyard) Solar
Solar
208 MWPaused / redesign Franklin, TXERCOT Jan 2021target 2026
Rockefeller Solar
Solar
208 MWPaused / redesign Schleicher, TXERCOT Oct 2019target 2027
Erath County Solar
Solar · Erath County Solar, LLC
207 MWAgreement signed Erath, TXERCOT Mar 2021target 2029
St. Gall Solar
Solar · St. Gall Solar LLC
207 MWIn study Pecos, TXERCOT Feb 2022target 2026
Hoyte Solar
Solar · Milano Solar LLC
207 MWAgreement signed Milam, TXERCOT Apr 2021target 2027
Fountain Point Solar
Solar · Fountain Point Solar Energy LLC
207 MWIn study Union, OHPJM Aug 2018target 2021
Page 11 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)