Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,067161.4 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,067 requests · page 10 of 22
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 962635, Chesterfield County
Solar · Duke Energy Progress LLC
80.0 MWIn study Chesterfield, SCSoutheast Sep 2024
Other project PP00043, Jones County
Other
80.0 MWIn study Jones, NCSoutheast Aug 2025target 2029
Solar project 962748, Jones County
Solar
80.0 MWIn study Jones, NCSoutheast Oct 2024
Solar project IC-1083, Marengo County
Solar
80.0 MWPaused / redesign Marengo, ALSoutheast Oct 2022target 2026
Solar project IC-1039, Dallas County
Solar
80.0 MWPaused / redesign Dallas, ALSoutheast May 2022target 2026
Solar project 196564, Davidson County
Solar
80.0 MWAgreement signed Davidson, NCSoutheast Jan 2022
Solar project IC-1132, Hale County
Solar
80.0 MWPaused / redesign Hale, ALSoutheast Mar 2023target 2027
Solar + storage project IC-1060, Marengo County
Solar + storage
80.0 MWPaused / redesign Marengo, ALSoutheast Sep 2022target 2027
Solar project 564510, Bladen County
Solar
80.0 MWAgreement signed Bladen, NCSoutheast Jun 2022target 2027
Other project PP00035, Wilson County
Other
80.0 MWIn study Wilson, NCSoutheast Jun 2025target 2029
Other project PP00051, Duplin County
Other
80.0 MWIn study Duplin, NCSoutheast Aug 2025target 2029
Solar project 915751, Granville County
Solar
80.0 MWIn study Granville, NCSoutheast Sep 2023
Solar + storage project IC-971, Lowndes County
Solar + storage
80.0 MWPaused / redesign Lowndes, ALSoutheast Jul 2021target 2026
Solar + storage project IC-954, Conecuh County
Solar + storage
80.0 MWPaused / redesign Conecuh, ALSoutheast Apr 2021target 2026
Solar project 917443, Scotland County
Solar
80.0 MWAgreement signed Scotland, NCSoutheast Sep 2023
Solar + storage project IC-1053, Hale County
Solar + storage
80.0 MWPaused / redesign Hale, ALSoutheast Aug 2022target 2027
Solar project IC-1224, Baldwin County
Solar
80.0 MWAgreement signed Baldwin, ALSoutheast Jan 2024target 2028
Solar project 569890, Wayne County
Solar
80.0 MWAgreement signed Wayne, NCSoutheast Jun 2022target 2029
Other project PP00042, Granville County
Other
80.0 MWIn study Granville, NCSoutheast Jun 2025target 2027
Solar + storage project IC-997, Baldwin County
Solar + storage
80.0 MWPaused / redesign Baldwin, ALSoutheast Dec 2021target 2026
Solar + storage project IC-1000, Baldwin County
Solar + storage
80.0 MWPaused / redesign Baldwin, ALSoutheast Dec 2021target 2026
Solar + storage project IC-1087, Russell County
Solar + storage
80.0 MWPaused / redesign Russell, ALSoutheast Nov 2022target 2026
Solar + storage project IC-979, Conecuh County
Solar + storage
80.0 MWPaused / redesign Conecuh, ALSoutheast Aug 2021target 2026
Solar project IC-1001, Early County
Solar
80.0 MWPaused / redesign Early, GASoutheast Dec 2021target 2025
Other project PP00044, Duplin County
Other
80.0 MWIn study Duplin, NCSoutheast Aug 2025target 2029
Solar project 569632, Scotland County
Solar
80.0 MWUnder construction Scotland, NCSoutheast Jun 2022target 2026
Solar project 948720, Nash County
Solar · Duke Energy Progress, LLC
80.0 MWUnder construction Nash, NCSoutheast Jun 2017target 2025
Solar + storage project IC-1052, Lee County
Solar + storage
80.0 MWPaused / redesign Lee, ALSoutheast Aug 2022target 2026
Solar project 977272, Wayne County
Solar
80.0 MWIn study Wayne, NCSoutheast Jun 2025
Solar project IC-1036, Montgomery County
Solar
80.0 MWPaused / redesign Montgomery, ALSoutheast May 2022target 2027
Solar project GI-127, Ralls County
Solar
80.0 MWIn study Ralls, MOSoutheast May 2025target 2028
Solar project 977914, Columbus County
Solar
80.0 MWIn study Columbus, NCSoutheast Jun 2025
SR Metter
Solar
80.0 MWUnder construction Candler, GASoutheast Oct 20192022
Solar project IC-943, Talladega County
Solar
80.0 MWPaused / redesign Talladega, ALSoutheast Mar 2021target 2025
Solar project IC-926, Montgomery County
Solar
80.0 MWPaused / redesign Montgomery, ALSoutheast Dec 2020target 2027
Solar project 962971, Duplin County
Solar
80.0 MWIn study Duplin, NCSoutheast Oct 2024
Solar project 292, Lake County
Solar
80.0 MWAgreement signed Lake, TNSoutheast Apr 2016target 2023
Solar + storage project IC-1061, Marengo County
Solar + storage
80.0 MWPaused / redesign Marengo, ALSoutheast Sep 2022target 2027
Solar project IC-1075, Dallas County
Solar
80.0 MWPaused / redesign Dallas, ALSoutheast Oct 2022target 2027
Solar project IC-894, Wheeler County
Solar
80.0 MWAgreement signed Wheeler, GASoutheast Jul 2020target 2026
Solar + storage project IC-1086, Perry County
Solar + storage
80.0 MWPaused / redesign Perry, ALSoutheast Nov 2022target 2026
Solar project IC-975, Dale County
Solar
80.0 MWPaused / redesign Dale, ALSoutheast Jul 2021target 2025
Solar project IC-1128, Perry County
Solar
79.9 MWAgreement signed Perry, ALSoutheast Mar 2023target 2027
Solar project IC-1121, Montgomery County
Solar
79.9 MWPaused / redesign Montgomery, ALSoutheast Mar 2023target 2027
Solar project IC-1127, Perry County
Solar
79.9 MWAgreement signed Perry, ALSoutheast Mar 2023target 2027
Solar project IC-1122, Montgomery County
Solar
79.9 MWPaused / redesign Montgomery, ALSoutheast Mar 2023target 2027
Solar project 25-IC-1372, Elbert County
Solar
79.0 MWIn study Elbert, GASoutheast Apr 2025target 2030
Solar project IC-1002, Decatur County
Solar
78.0 MWPaused / redesign Decatur, GASoutheast Dec 2021target 2025
Gas project 417, Volusia County
Gas · FPL
76.0 MWIn study Volusia, FLSoutheast Sep 2020target 2025
Gas project 20230829006, Jasper County
Gas · DESC - Generation
76.0 MWIn study Jasper, SCSoutheast target 2023
Page 10 of 22

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)