🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Georgia

SOLAR · SOUTHEAST

Solar project IC-1001, Early County

Solar project IC-1001, Early County is a 80.0 MW solar request suspended in the Southeast interconnection queue, in Early County, Georgia, connecting to Southern Company.

Queue statusPaused / redesign
  1. PlanningQueued Dec 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IC-1001
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Blakely Primary - Webb 115 kV Line
Location
Early County, Georgia
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Energy only (ERIS)
Queue status
Suspended
Entered queue
8 December 2021
Proposed online date
August 2025

Location

Marker shows the centre of Early County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Early County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem