🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Georgia

SOLAR · SOUTHEAST

SR Arlington I

SR Arlington I is a 20.0 MW solar request built and operating in the Southeast interconnection queue, in Early County, Georgia, connecting to Georgia Transmission.

Queue statusOperating
  1. PlanningQueued Dec 2023 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-129
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Giles 115 kV Substation
Location
Early County, Georgia
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
31 December 2023

Location

Marker shows the centre of Early County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Early County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem