SOLAR Β· SOUTHEAST

Solar project IC-883, Early County

Solar project IC-883, Early County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Early County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2020 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-883
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Blakely Primary - Spring Creek 115 kV Line
Location
Early County, Georgia
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
13 July 2020
Proposed online date
June 2023
Withdrawn
May 2023

Location

Marker shows the centre of Early County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Early County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem