SR Arlington II

SR Arlington II is a 109 MW solar request built and operating in the Southeast interconnection queue, in Early County, Georgia, connecting to Georgia Transmission.

Queue statusOperating
  1. PlanningQueued Dec 2023 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-108
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Giles 115 kV Substation
Location
Early County, Georgia
Technology
Solar: 109 MW
Total requested
109 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
31 December 2023

Location

Marker shows the centre of Early County; the queue data does not give exact sites.