United States › Grid › Interconnection queues › Alabama
SOLAR · SOUTHEASTSolar project IC-1083, Marengo County
Solar project IC-1083, Marengo County is a 80.0 MW solar request suspended in the Southeast interconnection queue, in Marengo County, Alabama, connecting to Southern Company.
Queue statusPaused / redesign
- PlanningQueued Oct 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- IC-1083
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Demopolis - Selma 115 kV Line
- Location
- Marengo County, Alabama
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Energy only (ERIS)
- Queue status
- Suspended
- Entered queue
- 26 October 2022
- Proposed online date
- June 2026
Location
Marker shows the centre of Marengo County; the queue data does not give exact sites.
Other requests in Marengo County
- Solar + storage project IC-1234, Marengo CountySolar + storage · 175 MW · suspended
- Solar + storage project IC-1072, Marengo CountySolar + storage · 80.0 MW · suspended
- Solar + storage project IC-1060, Marengo CountySolar + storage · 80.0 MW · suspended
- Solar + storage project IC-1061, Marengo CountySolar + storage · 80.0 MW · suspended
- Solar + storage project IC-852, Marengo CountySolar + storage · 220 MW · withdrawn
- Solar project IC-814, Marengo CountySolar · 220 MW · withdrawn
- Solar project 25-IC-1362, Marengo CountySolar · 195 MW · withdrawn
- Solar project IC-804, Marengo CountySolar · 100 MW · withdrawn
- Solar + storage project IC-1062, Marengo CountySolar + storage · 80.0 MW · withdrawn
- Solar project IC-1004, Marengo CountySolar · 80.0 MW · withdrawn
- Solar project IC-717, Marengo CountySolar · 80.0 MW · withdrawn
- Solar + storage project IC-985, Marengo CountySolar + storage · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem