SOLAR + STORAGE Β· SOUTHEASTSolar + storage project IC-1062, Marengo County
Solar + storage project IC-1062, Marengo County is a 80.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Marengo County, Alabama, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedNov 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-1062
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Bellamy - Demopolis 115 kV Line
- Location
- Marengo County, Alabama
- Technology
- Solar: 80.0 MW Β· Battery
- Total requested
- 80.0 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 7 September 2022
- Withdrawn
- November 2022
Location
Marker shows the centre of Marengo County; the queue data does not give exact sites.
Other requests in Marengo County
- Solar + storage project IC-1234, Marengo CountySolar + storage Β· 175 MW Β· suspended
- Solar + storage project IC-1072, Marengo CountySolar + storage Β· 80.0 MW Β· suspended
- Solar project IC-1083, Marengo CountySolar Β· 80.0 MW Β· suspended
- Solar + storage project IC-1060, Marengo CountySolar + storage Β· 80.0 MW Β· suspended
- Solar + storage project IC-1061, Marengo CountySolar + storage Β· 80.0 MW Β· suspended
- Solar + storage project IC-852, Marengo CountySolar + storage Β· 220 MW Β· withdrawn
- Solar project IC-814, Marengo CountySolar Β· 220 MW Β· withdrawn
- Solar project 25-IC-1362, Marengo CountySolar Β· 195 MW Β· withdrawn
- Solar project IC-804, Marengo CountySolar Β· 100 MW Β· withdrawn
- Solar project IC-1004, Marengo CountySolar Β· 80.0 MW Β· withdrawn
- Solar project IC-717, Marengo CountySolar Β· 80.0 MW Β· withdrawn