SOLAR · SOUTHEASTSolar project 948720, Nash County
Solar project 948720, Nash County is a 80.0 MW solar request under construction in the Southeast interconnection queue, in Nash County, North Carolina, connecting to Duke Energy Progress.
Queue statusUnder construction
- PlanningQueued Jun 2017 (completed)
- Consented (completed)
- Construction (current stage)
- OperatingTarget Jul 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 948720
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Progress
- Developer
- Duke Energy Progress, LLC
- Location
- Nash County, North Carolina
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Construction - In Progress
- Queue status
- Active
- Entered queue
- 16 June 2017
- Proposed online date
- July 2025
Location
Marker shows the centre of Nash County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Nash County
- Battery storage project 956218, Nash CountyBattery storage · 50.0 MW · in study
- Other project PP00038, Nash CountyOther · 50.0 MW · in study
- Whitakers Solar ParkSolar · 12.0 MW · built
- Battery storage project 565492, Nash CountyBattery storage · 138 MW · withdrawn
- Solar project 956958, Nash CountySolar · 78.3 MW · withdrawn
- Solar project 564638, Nash CountySolar · 78.3 MW · withdrawn
- Solar project 30708, Nash CountySolar · 78.3 MW · withdrawn
- Solar project 910009, Nash CountySolar · 78.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem