United States › Grid › Interconnection queues › Alabama
SOLAR · SOUTHEASTSolar project IC-975, Dale County
Solar project IC-975, Dale County is a 80.0 MW solar request suspended in the Southeast interconnection queue, in Dale County, Alabama, connecting to Southern Company.
Queue statusPaused / redesign
- PlanningQueued Jul 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- IC-975
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Pinckard – Pike County 230 kV Line
- Location
- Dale County, Alabama
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Queue status
- Suspended
- Entered queue
- 22 July 2021
- Proposed online date
- October 2025
Location
Marker shows the centre of Dale County; the queue data does not give exact sites.
Other requests in Dale County
- Solar project 25-IC-1366, Dale CountySolar · 110 MW · in study
- Solar project 25-IC-1354, Dale CountySolar · 91.0 MW · in study
- Solar project IC-1066, Dale CountySolar · 80.0 MW · suspended
- Gas project IC-088, Dale CountyGas · 640 MW · withdrawn
- Gas project IC-073, Dale CountyGas · 620 MW · withdrawn
- Solar project IC-413, Dale CountySolar · 80.0 MW · withdrawn
- Solar project IC-796, Dale CountySolar · 79.8 MW · withdrawn
- Solar project IC-470, Dale CountySolar · 79.7 MW · withdrawn
- Solar project IC-450, Dale CountySolar · 79.7 MW · withdrawn
- Solar + storage project IC-931, Dale CountySolar + storage · 79.0 MW · withdrawn
- Solar + storage project IC-928, Dale CountySolar + storage · 79.0 MW · withdrawn
- Solar project IC-693, Dale CountySolar · 78.2 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem