Solar project IC-470, Dale County

Solar project IC-470, Dale County is a 79.7 MW solar request withdrawn in the Southeast interconnection queue, in Dale County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2016 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. ConsentedFeb 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-470
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Dothan - Pinckard #2 115 kV Line
Location
Dale County, Alabama
Technology
Solar: 79.7 MW
Total requested
79.7 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
8 July 2016
Agreement signed
20 February 2019
Withdrawn
March 2022

Location

Marker shows the centre of Dale County; the queue data does not give exact sites.