United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project IC-931, Dale County

Solar + storage project IC-931, Dale County is a 79.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Dale County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2021 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-931
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Dothan - Pinckard 115 kV Line
Location
Dale County, Alabama
Technology
Solar: 79.0 MW Β· Battery
Total requested
79.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
14 January 2021
Withdrawn
November 2023

Location

Marker shows the centre of Dale County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Dale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem