Solar + storage project IC-928, Dale County

Solar + storage project IC-928, Dale County is a 79.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Dale County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2021 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-928
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Enterprise - Pinckard #1 115 kV Line
Location
Dale County, Alabama
Technology
Solar: 79.0 MW Β· Battery
Total requested
79.0 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
14 January 2021
Proposed online date
August 2029
Withdrawn
December 2025

Location

Marker shows the centre of Dale County; the queue data does not give exact sites.