πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

SOLAR Β· SOUTHEAST

Solar project IC-450, Dale County

Solar project IC-450, Dale County is a 79.7 MW solar request withdrawn in the Southeast interconnection queue, in Dale County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. ConsentedMar 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-450
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Dothan - Pinckard #2 115 kV Line
Location
Dale County, Alabama
Technology
Solar: 79.7 MW
Total requested
79.7 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
31 March 2016
Agreement signed
5 March 2019
Withdrawn
March 2021

Location

Marker shows the centre of Dale County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Dale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem