Solar project 977272, Wayne County

Solar project 977272, Wayne County is a 80.0 MW solar request in interconnection study in the Southeast interconnection queue, in Wayne County, North Carolina, connecting to Duke Energy Progress.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
977272
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
LEE SUB - WOMMACK 230KV SOUTH
Location
Wayne County, North Carolina
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Other
Study phase
Phase 1 Cluster Study - Study Complete
Queue status
Active
Entered queue
27 June 2025

Location

Marker shows the centre of Wayne County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Wayne County