United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESCompleted queue projects in ERCOT (Texas) — page 10
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Republic Road Storage Other · KCE TX 11, LLC |
51.8 MW | |
| Lily Storage Other · Lily Solar, LLC |
51.7 MW | |
| Blue Jay BESS Other · Blue Jay Solar I, LLC |
51.6 MW | |
| Roseland Storage Other · Enel Green Power Roseland Solar, LLC |
51.6 MW | |
| Endurance Park Storage Other · KCE TX 13, LLC |
51.5 MW | |
| River Valley Storage 2 Other · KCE TX 21, LLC |
51.5 MW | |
| River Valley Storage 1 Other · KCE TX 19, LLC |
51.5 MW | |
| Sky Global Power One Gas · Sky Global Power |
51.4 MW | |
| High Lonesome BESS Other · High Lonesome Storage, LLC |
51.1 MW | |
| Padua Grid BESS Battery storage · Padua Grid, LLC |
51.1 MW | |
| Queen BESS Other · Roadrunner Storage, LLC |
51.1 MW | |
| Hidalgo II Wind Onshore wind · EDP Renewables |
51.0 MW | |
| RABBS U2 Power Station Gas |
51.0 MW | |
| RABBS U1 Power Station Gas · Braes Bayou II, LLC |
51.0 MW | |
| RABBS U6 Power Station Gas |
51.0 MW | |
| Gransolar Texas One Solar · Gransolar Texas One, LLC |
50.8 MW | |
| Byrd Ranch Energy Storage Plant Other · Byrd Ranch Storage LLC |
50.6 MW | |
| High Lonesome Wind Phase II Onshore wind · HIGH LONESOME WIND POWER, LLC |
50.6 MW | |
| Tortolas BESS Other · BRP Tortolas BESS LLC |
50.3 MW | |
| Lasso Solar · Solaire Direct |
50.0 MW | |
| Teco GTG2 Gas · Thermal Energy Corp. |
50.0 MW | |
| SIRIUS_UNIT2 (Pearl Solar) Solar · OCI Solar |
50.0 MW | |
| Frontera Chillers Gas · Direct Energy |
50.0 MW | |
| TECO Central Plant Gas · Thermal Energy Corporation |
50.0 MW | |
| Roughneck Storage Other · KCE TX 23, LLC |
50.0 MW | |
| Brightside Solar Solar · Brightside Solar, LLC |
50.0 MW | |
| Lamesa Solar B (Phase II) IVORY Solar · OCI Solar |
50.0 MW | |
| OCI Alamo 1 Solar · OCI Alamo 1 LLC |
50.0 MW | |
| Cotton Plains Wind Onshore wind · Apex Clean |
50.0 MW | |
| Pitts Dudik Solar Solar · Elawan Pitts Dudik Solar, LLC |
49.6 MW | |
| Dansby3 Gas · Bryan Texas Utilities |
48.0 MW | |
| Vancourt Solar Solar · Rayos Del Sol Solar Project, LLC |
45.7 MW | |
| Colorado Bend 2 repower Gas |
45.0 MW | |
| TAMU Combined Heat & Power Gas · Texas A&M |
45.0 MW | |
| Oak Grove Units 1 & 2 repower Coal |
45.0 MW | |
| Lufkin Gas · Aspen Power LLC |
45.0 MW | |
| Wolf Hollow 2 repower Gas |
44.0 MW | |
| Zier Storage Other · Zier Solar, LLC |
40.4 MW | |
| Eunice Storage Other · 2W Permian Solar LLC |
40.3 MW | |
| Jungmann Solar Solar · BT Jungmann LLC |
40.2 MW | |
| OCI Alamo 4 (Brackettville / ECLIPSE) Solar · OCI Solar Power LLC |
38.0 MW | |
| Notrees Battery Storage Battery storage · Duke Energy Renewables, Inc |
36.0 MW | |
| Forney Upgrade Gas · Nextera |
34.0 MW | |
| Vera Wind V110 Onshore wind · Longroad Energy |
34.0 MW | |
| V4 Palo Alto DGR Other · Life Cycle Power |
33.0 MW | |
| S_Hills Wind Onshore wind · SEYMOUR HILLS WIND PROJECT, LLC |
30.2 MW | |
| Pyron BESS II Other · Pyron Wind Farm, LLC |
30.2 MW | |
| FRV AE Solar Solar · FRV AE Solar, LLC |
30.0 MW | |
| BlueBell Solar Solar · Nextera |
30.0 MW | |
| Sandow Unit 5 Coal · Luminant |
30.0 MW |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- Southeast (non-ISO utilities)529 · 112.4 GW
- PJM (Mid-Atlantic, Midwest)1,192 · 97.6 GW
- ERCOT (Texas)613 · 95.3 GW
- MISO (Midcontinent)514 · 69.7 GW
- West (non-ISO utilities)963 · 64.7 GW
- SPP (Southwest Power Pool)299 · 45.1 GW
- CAISO (California)234 · 37.6 GW
- NYISO (New York)215 · 24.8 GW
- ISO-NE (New England)228 · 16.5 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)