OCI Alamo 4 (Brackettville / ECLIPSE)

OCI Alamo 4 (Brackettville / ECLIPSE) is a 38.0 MW solar request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Mar 2012 (completed)
  2. ConsentedJan 2014 (completed)
  3. Construction (completed)
  4. OperatingAug 2014 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
14INR0024
Grid region
ERCOT (Texas)
Developer
OCI Solar Power LLC
Technology
Solar: 38.0 MW
Total requested
38.0 MW
Study phase
IA
Queue status
Operational
Entered queue
8 March 2012
Agreement signed
7 January 2014
Proposed online date
August 2014
Came online
August 2014

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem