Blue Jay BESS

Blue Jay BESS is a 51.6 MW other request built and operating in the ERCOT interconnection queue, in Grimes County, Texas.

Queue statusOperating
  1. PlanningQueued Jan 2020 (completed)
  2. ConsentedJan 2022 (completed)
  3. Construction (completed)
  4. OperatingJun 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0019
Grid region
ERCOT (Texas)
Developer
Blue Jay Solar I, LLC
Connection point (POI)
4 IOLA 138kV
Location
Grimes County, Texas
Technology
Other: 51.6 MW
Total requested
51.6 MW
Study phase
IA
Queue status
Operational
Entered queue
5 January 2020
Agreement signed
24 January 2022
Proposed online date
June 2023
Came online
June 2023

Location

Marker shows the centre of Grimes County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Grimes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem