πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· ERCOT

Notrees Battery Storage

Notrees Battery Storage is a 36.0 MW battery storage request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued May 2011 (completed)
  2. ConsentedJun 2012 (completed)
  3. Construction (completed)
  4. OperatingJan 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
12INR0076
Grid region
ERCOT (Texas)
Developer
Duke Energy Renewables, Inc
Connection point (POI)
NWF_NWF1 34.500
Technology
Battery: 36.0 MW
Total requested
36.0 MW
Study phase
IA
Queue status
Operational
Entered queue
3 May 2011
Agreement signed
21 June 2012
Proposed online date
January 2013
Came online
January 2013

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem