Brightside Solar

Brightside Solar is a 50.0 MW solar request built and operating in the ERCOT interconnection queue, in Bee County, Texas.

Queue statusOperating
  1. PlanningQueued Feb 2017 (completed)
  2. ConsentedJun 2020 (completed)
  3. Construction (completed)
  4. OperatingMay 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
18INR0060
Grid region
ERCOT (Texas)
Developer
Brightside Solar, LLC
Connection point (POI)
tap 69kV 8198 Beeville - 8400 Three River
Location
Bee County, Texas
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Study phase
IA
Queue status
Operational
Entered queue
16 February 2017
Agreement signed
11 June 2020
Proposed online date
May 2022
Came online
May 2022

Location

Marker shows the centre of Bee County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem