πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

SIRIUS_UNIT2 (Pearl Solar)

SIRIUS_UNIT2 (Pearl Solar) is a 50.0 MW solar request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Dec 2013 (completed)
  2. ConsentedDec 2014 (completed)
  3. Construction (completed)
  4. OperatingOct 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
15INR0070_1b
Grid region
ERCOT (Texas)
Developer
OCI Solar
Connection point (POI)
132436 Sirius2 34.5kV
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Study phase
IA
Queue status
Operational
Entered queue
23 December 2013
Agreement signed
17 December 2014
Proposed online date
October 2017
Came online
October 2017

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem