United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTGransolar Texas One
Gransolar Texas One is a 50.8 MW solar request built and operating in the ERCOT interconnection queue, in Milam County, Texas.
Request details
- Queue ID
- 22INR0511
- Grid region
- ERCOT (Texas)
- Developer
- Gransolar Texas One, LLC
- Connection point (POI)
- Tap 138kV 3659 Thorndale North - 116 Salty
- Location
- Milam County, Texas
- Technology
- Solar: 50.8 MW
- Total requested
- 50.8 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 15 March 2021
- Agreement signed
- 13 June 2022
- Proposed online date
- September 2025
- Came online
- December 2024
Location
Marker shows the centre of Milam County; the queue data does not give exact sites.
Other requests in Milam County
- Sypert Branch Solar ProjectSolar · 261 MW · agreement signed
- Eastbell Milam SolarSolar · 245 MW · agreement signed
- Adelite StorageBattery storage · 232 MW · agreement signed
- Hoyte SolarSolar · 207 MW · agreement signed
- Stoneridge SolarSolar · 202 MW · agreement signed
- Yaupon Solar SLFSolar · 201 MW · agreement signed
- Camino Santiago SolarSolar · 196 MW · agreement signed
- Dos Rios Energy Storage SLFBattery storage · 165 MW · agreement signed
- Eastbell Milam Solar IISolar · 151 MW · agreement signed
- Happy Dog StorageSolar + storage · 105 MW · agreement signed
- Stoneridge BESSBattery storage · 102 MW · agreement signed
- HappyDogSolarSolar + storage · 85.5 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem