United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OTHER Β· ERCOT

Roseland Storage

Roseland Storage is a 51.6 MW other request built and operating in the ERCOT interconnection queue, in Falls County, Texas.

Queue statusOperating
  1. PlanningQueued Dec 2019 (completed)
  2. ConsentedJan 2022 (completed)
  3. Construction (completed)
  4. OperatingJul 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0280
Grid region
ERCOT (Texas)
Developer
Enel Green Power Roseland Solar, LLC
Connection point (POI)
tap 345kV 3390 Jewett - 3399 Ratsnake
Location
Falls County, Texas
Technology
Other: 51.6 MW
Total requested
51.6 MW
Study phase
IA
Queue status
Operational
Entered queue
25 December 2019
Agreement signed
26 January 2022
Proposed online date
July 2023
Came online
July 2023

Location

Marker shows the centre of Falls County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Falls County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem