Jungmann Solar

Jungmann Solar is a 40.2 MW solar request built and operating in the ERCOT interconnection queue, in Milam County, Texas.

Queue statusOperating
  1. PlanningQueued Jun 2020 (completed)
  2. ConsentedFeb 2022 (completed)
  3. Construction (completed)
  4. OperatingDec 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0356
Grid region
ERCOT (Texas)
Developer
BT Jungmann LLC
Connection point (POI)
Tap 69kV 3643 Temp SS - 3689 Marak c1
Location
Milam County, Texas
Technology
Solar: 40.2 MW
Total requested
40.2 MW
Study phase
IA
Queue status
Operational
Entered queue
2 June 2020
Agreement signed
15 February 2022
Proposed online date
September 2025
Came online
December 2024

Location

Marker shows the centre of Milam County; the queue data does not give exact sites.