RABBS U1 Power Station

RABBS U1 Power Station is a 51.0 MW gas request built and operating in the ERCOT interconnection queue, in Fort Bend County, Texas.

Queue statusOperating
  1. Planning (completed)
  2. ConsentedNov 2020 (completed)
  3. Construction (completed)
  4. OperatingSep 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0604
Grid region
ERCOT (Texas)
Developer
Braes Bayou II, LLC
Connection point (POI)
44650 Smithers 345kV
Location
Fort Bend County, Texas
Technology
Gas: 51.0 MW
Total requested
51.0 MW
Study phase
IA
Queue status
Operational
Agreement signed
18 November 2020
Proposed online date
September 2022
Came online
September 2022

Location

Marker shows the centre of Fort Bend County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Fort Bend County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem