Oak Grove Units 1 & 2 repower

Oak Grove Units 1 & 2 repower is a 45.0 MW coal request built and operating in the ERCOT interconnection queue, in Robertson County, Texas.

Queue statusOperating
  1. PlanningQueued Jan 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0204
Grid region
ERCOT (Texas)
Location
Robertson County, Texas
Technology
Coal: 45.0 MW
Total requested
45.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
27 January 2019
Came online
June 2019

Location

Marker shows the centre of Robertson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas