Battery storage interconnection queue in the USA (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9912.0 GW
Active in queue12.0 GW99 requests
Agreement signed9,097 MW63 requests
Withdrawn29329.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

99 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Irving Storage
Battery storage
783 MWAgreement signed Monterey, CACAISO May 2019target 2025
Menifee Power Bank
Battery storage
680 MWAgreement signed Riverside, CACAISO Apr 2019target 2025
Double Butte Storage
Battery storage
508 MWAgreement signed Riverside, CACAISO Apr 2019target 2030
Goldback Solar Center
Battery storage
500 MWAgreement signed Ventura, CACAISO Apr 2019target 2026
Jewelflower Storage
Battery storage
355 MWAgreement signed Santa Clara, CACAISO Apr 2019target 2029
Humidor Storage 1
Battery storage
305 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2028
Battery storage project Q314, Maricopa County
Battery storage
300 MWIn study Maricopa, AZWest Sep 2019target 2022
Nighthawk Storage
Battery storage
300 MWAgreement signed San Diego, CACAISO Apr 2019target 2026
Medway Grid Battery Storage
Battery storage
250 MWAgreement signed Norfolk, MAISO-NE Mar 2019target 2025
Commerce Energy Storage
Battery storage
250 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2026
Cormorant Storage
Battery storage
250 MWAgreement signed San Francisco, CACAISO Apr 2019target 2027
Battery storage project GEN-2019-011, Yoakum County
Battery storage
207 MWAgreement signed Yoakum, TXSPP Apr 2019target 2028
Rockefeller Storage
Battery storage ยท Mittel Rockefeller Storage LLC
207 MWAgreement signed Schleicher, TXERCOT Oct 2019target 2027
Prospect Power
Battery storage
200 MWAgreement signed Rockingham, VAPJM May 2019target 2026
Flint Grid
Battery storage
200 MWAgreement signed Licking, OHPJM Jul 2019target 2027
Kestrel Storage
Battery storage
200 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2027
Hudson Energy Storage Facility
Battery storage
200 MWAgreement signed Hudson, NJPJM Sep 2019target 2028
Union City Storage I
Battery storage
200 MWIn study Fulton, GASoutheast Dec 20192022
Battery storage project GEN-2019-012, Woodward County
Battery storage
200 MWAgreement signed Woodward, OKSPP May 2019target 2027
Sandpiper Storage
Battery storage
200 MWAgreement signed Orange, CACAISO Apr 2019target 2026
Tanager Storage
Battery storage
200 MWAgreement signed Santa Clara, CACAISO Apr 2019target 2027
Avocet Storage
Battery storage
200 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2026
Battery storage project GEN-2019-065, Smith County
Battery storage
180 MWIn study Smith, TXSPP May 2019target 2026
Lamberton Road Battery
Battery storage
170 MWAgreement signed Mercer, NJPJM Sep 2019target 2027
Energy Storage
Battery storage
170 MWAgreement signed Norfolk, MAISO-NE Apr 2019target 2027
Carol Battery
Battery storage
168 MWPaused / redesign Potter, TXERCOT Jun 2019
Battery storage project J1355, Laporte County
Battery storage
160 MWAgreement signed Laporte, INMISO Apr 2019target 2026
Erie East Energy
Battery storage
160 MWPaused / redesign Erie, PAPJM Mar 2019target 2026
Battery storage project Q299, Maricopa County
Battery storage
150 MWAgreement signed Maricopa, AZWest Mar 2019target 2023
Battery storage project IA-PNM-2019-19, Bernalillo County
Battery storage ยท PNM โ€šร„รฌ Generation
150 MWAgreement signed Bernalillo, NMWest Apr 2019target 2021
Battery storage project J1357, Madison County
Battery storage
150 MWAgreement signed Madison, INMISO Apr 2019target 2025
Battery storage project J1354, Decatur County
Battery storage
146 MWAgreement signed Decatur, INMISO Apr 2019target 2025
Battery storage project J1358, Laporte County
Battery storage
125 MWAgreement signed Laporte, INMISO Apr 2019target 2026
Trinidad ESS Addition
Battery storage
110 MWPaused / redesign Henderson, TXERCOT Dec 2019target 2026
Holtsville 138kV Energy Storage
Battery storage ยท Holtsville Energy Storage, LLC
110 MWIn study Suffolk, NYNYISO Dec 2019target 2026
Coleto Creek ESS Addition
Battery storage
100 MWPaused / redesign Goliad, TXERCOT Dec 2019
Independence Trail Storage
Battery storage ยท KCE TX 16, LLC
100 MWIn study Childress, TXERCOT Dec 2019target 2028
Battery storage project IA-PNM-2019-18, Bernalillo County
Battery storage
100 MWPaused / redesign Bernalillo, NMWest Apr 2019target 2022
Harwood Power
Battery storage
100 MWAgreement signed King George, VAPJM Oct 2019target 2029
Astoria Energy Storage
Battery storage ยท East River ESS, LLC
100 MWIn study Queens, NYNYISO Oct 2019target 2026
Threeforks Energy Storage
Battery storage
100 MWAgreement signed Martin, KYPJM Sep 2019target 2028
Union City Storage II
Battery storage
100 MWIn study Fulton, GASoutheast Dec 20192022
Yadkins Energy Center
Battery storage ยท Yadkins Energy Center, LLC
100 MWIn study City Of Chesapeake, VAPJM Mar 2019target 2021
Battery storage project 38056, Wake County
Battery storage ยท Knightdale Energy Center, LLC
100 MWAgreement signed Wake, NCSoutheast Jun 2019
Battery storage project Company JW, Washoe County
Battery storage
100 MWAgreement signed Washoe, NVWest Sep 2019target 2027
Noosa Energy Storage
Battery storage
99.0 MWAgreement signed San Joaquin, CACAISO Apr 2019target 2029
Kce NY 5
Battery storage ยท KCE NY 5 LLC
94.0 MWIn study Ulster, NYNYISO Dec 2019target 2027
Battery storage project Q297, Yuma County
Battery storage
90.1 MWIn study Yuma, AZWest Mar 2019target 2022
Harlem River Yard
Battery storage ยท Harlem River ESS, LLC
79.9 MWIn study Queens, NYNYISO Sep 2019target 2028
Luyster Creek Energy Storage 2
Battery storage ยท Eastern Generation, LLC
79.0 MWIn study Queens, NYNYISO May 2019target 2027
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)