United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESQueue requests in study in the USA (2018 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Maidsville CCGT Gas |
1,270 MW | Paused / redesign |
| Battery storage project G0608, Klickitat County Battery storage |
1,200 MW | In study |
| Solar project Q274, Coconino County Solar |
1,000 MW | In study |
| Sunrise Wind Offshore wind ยท Sunrise Wind LLC |
880 MW | In study |
| Offshore Wind Offshore wind |
827 MW | In study |
| Ocean Wind Offshore wind |
816 MW | Paused / redesign |
| Empire Wind 1 Offshore wind ยท Empire Offshore Wind LLC |
816 MW | In study |
| Onshore wind project 356, Rosebud County Onshore wind |
750 MW | In study |
| Onshore wind project 357, Rosebud County Onshore wind |
750 MW | In study |
| Arida Solar Farm Solar + storage |
740 MW | In study |
| Gas project JEA-Q008, Duval County Gas |
645 MW | In study |
| Vulcan Solar + storage |
500 MW | In study |
| Onshore wind project Q273, Navajo County Onshore wind |
477 MW | In study |
| Ocean Wind LLC Offshore wind |
432 MW | Paused / redesign |
| Green Holly Solar Solar ยท Copenhagen Infrastructure Partners Fund IV |
414 MW | Paused / redesign |
| Solar + storage project Q09, Pinal County Solar + storage |
400 MW | In study |
| Battery storage project G0609, Multnomah County Battery storage |
400 MW | In study |
| Solar project G0589, Klickitat County Solar |
381 MW | In study |
| Solar + storage project 2018-G6 Solar + storage |
360 MW | In study |
| Solar + storage project Company 173, Clark County Solar + storage |
350 MW | Paused / redesign |
| Onshore wind project G0585, Klickitat County Onshore wind |
313 MW | In study |
| Other project 62, Pima County Other |
300 MW | In study |
| Arroyo Del Bisonte Solar Solar ยท Sunchase Power |
300 MW | Paused / redesign |
| Pierce Wind Onshore wind |
300 MW | Paused / redesign |
| Shifting Gale Wind Onshore wind |
289 MW | Paused / redesign |
| Excelsior Energy Center Solar ยท Excelsior Energy Center, LLC |
280 MW | In study |
| South Ripley Solar and BESS Solar + storage ยท ConnectGen Chautauqua County LLC |
270 MW | In study |
| Livingston Wind Onshore wind ยท Livingston Wind Project, LLC |
255 MW | In study |
| Solar project Company 170, Clark County Solar |
250 MW | Paused / redesign |
| Battery storage project Q278, Maricopa County Battery storage |
250 MW | In study |
| Gulf Wind 2 Onshore wind |
227 MW | Paused / redesign |
| Solar + storage project 2018-G41, Mohave County Solar + storage |
225 MW | In study |
| Solar + storage project 2018-G40, Mohave County Solar + storage |
225 MW | In study |
| Solar + storage project G0598, Klickitat County Solar + storage |
223 MW | In study |
| Walleye Solar Solar ยท Sandow Lakes Ranch Solar II, LLC |
215 MW | In study |
| Broomstick Solar Energy Centergy Center Solar |
210 MW | Paused / redesign |
| Fountain Point Solar Solar ยท Fountain Point Solar Energy LLC |
207 MW | In study |
| Rueter Solar Solar |
200 MW | Paused / redesign |
| Solar + storage project NC5-005, Clark County Solar + storage |
200 MW | In study |
| Battery storage project Q291, Maricopa County Battery storage |
200 MW | In study |
| Desert Rose Solar Solar |
200 MW | Paused / redesign |
| Battery storage project GEN-2018-025, Washington County Battery storage |
200 MW | Paused / redesign |
| Solar + storage project Q288, Maricopa County Solar + storage |
200 MW | In study |
| Battery storage project GEN-2018-033, Cass County Battery storage |
200 MW | Paused / redesign |
| Kce NY 2 Battery storage ยท KCE NY 2, LLC |
200 MW | In study |
| Lower Crossing Wind Onshore wind |
200 MW | Paused / redesign |
| Horseshoe Solar Solar ยท Horseshoe Solar Energy LLC |
180 MW | In study |
| Solar project G0602, Grant County Solar |
170 MW | In study |
| CAROL wind Onshore wind |
165 MW | Paused / redesign |
| Golden Aster Solar Energy Center Solar |
160 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)40 ยท 10.2 GW
- PJM (Mid-Atlantic, Midwest)34 ยท 5,884 MW
- NYISO (New York)15 ยท 3,444 MW
- ERCOT (Texas)16 ยท 2,703 MW
- Southeast (non-ISO utilities)13 ยท 1,590 MW
- CAISO (California)4 ยท 1,302 MW
- ISO-NE (New England)1 ยท 827 MW
- SPP (Southwest Power Pool)3 ยท 500 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)