🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arizona

SOLAR + STORAGE · CAISO

Vulcan

Vulcan is a 500 MW solar + storage request in interconnection study in the CAISO interconnection queue, in Maricopa County, Arizona, connecting to SDGE.

Queue statusIn planning
  1. PlanningQueued Apr 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1534
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Hassayampa Common Bus 500 kV
Location
Maricopa County, Arizona
Technology
Solar: 250 MW · Battery: 250 MW
Total requested
500 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
16 April 2018
Proposed online date
December 2027

Location

Marker shows the centre of Maricopa County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Maricopa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem