Battery storage project Q278, Maricopa County

Battery storage project Q278, Maricopa County is a 250 MW battery storage request in interconnection study in the West interconnection queue, in Maricopa County, Arizona, connecting to Arizona Public Service.

Queue statusIn planning
  1. PlanningQueued Jun 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q278
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Raceway 230kV Substation
Location
Maricopa County, Arizona
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Project with APS Project Manager
Queue status
Active
Entered queue
22 June 2018
Proposed online date
January 2021

Location

Marker shows the centre of Maricopa County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Maricopa County