🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

SOLAR + STORAGE · NYISO

South Ripley Solar and BESS

South Ripley Solar and BESS is a 270 MW solar + storage request in interconnection study in the NYISO interconnection queue, in Chautauqua County, New York, connecting to NM-NG.

Queue statusIn planning
  1. PlanningQueued Dec 2018 (current stage)
  2. ConsentedJan 2023 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
783
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
ConnectGen Chautauqua County LLC
Connection point (POI)
South Ripley Substation 230kV
Location
Chautauqua County, New York
Technology
Solar: 270 MW · Battery
Total requested
270 MW
Study phase
FES, SRIS, FS
Queue status
Active
Entered queue
7 December 2018
Agreement signed
11 January 2023
Proposed online date
December 2027

Location

Marker shows the centre of Chautauqua County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Chautauqua County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem