ONSHORE WIND Β· NYISO

Arkwright Summit

Arkwright Summit is a 78.4 MW onshore wind request built and operating in the NYISO interconnection queue, connecting to NM-NG.

Queue statusOperating
  1. PlanningQueued Nov 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
421
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Arkwright Summit Wind Farm LLC
Connection point (POI)
Dunkirk - Falconer 115 kV
Location
New York
Technology
Wind: 78.4 MW
Total requested
78.4 MW
Study phase
SRIS, FS
Queue status
Operational
Entered queue
1 November 2013

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem