United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Completed queue projects in the USA (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8910.4 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

89 requests · page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project PIS002, Carbon County
Onshore wind · PacifiCorp
400 MWOperating Carbon, WYWest Sep 2021target 2025
Solar + storage project Q376, Maricopa County
Solar + storage
400 MWOperating Maricopa, AZWest Mar 2021target 2024
Bear Swamp Pumping Load Increase
Battery storage
333 MWOperating Berkshire, MAISO-NE Nov 2021target 2021
Five Wells Solar
Solar · Five Wells Solar Center LLC
323 MWOperating Bell, TXERCOT Feb 20212023
Remy Jade Power Station
Gas · Remy Jade Generating, LLC
306 MWOperating Harris, TXERCOT Aug 20212024
Rodeo Ranch Energy Storage
Other · Rodeo Ranch Energy Storage, LLC
301 MWOperating Reeves, TXERCOT Sep 20212023
Solar + storage project Q389, Maricopa County
Solar + storage
300 MWOperating Maricopa, AZWest Mar 2021target 2023
Tanzanite Storage
Battery storage · Tanzanite Energy Storage LLC
266 MWOperating Henderson, TXERCOT Aug 20212025
Anole BESS
Battery storage · Anole Energy Storage, LLC
247 MWOperating Dallas, TXERCOT Jun 20212025
True North Solar
Solar · True North Solar LLC
239 MWOperating Falls, TXERCOT Jan 20212024
Shamrock
Onshore wind · Shamrock Interconnection LLC
224 MWOperating Crockett, TXERCOT Feb 20212023
Five Wells BESS
Other · Five Wells Storage LLC
221 MWOperating Bell, TXERCOT Feb 20212024
Stillhouse Solar
Solar · Stillhouse Solar LLC
211 MWOperating Bell, TXERCOT Nov 20212025
Holy ESS
Other · Citadel BESS LLC
209 MWOperating Harris, TXERCOT Nov 20212024
Callisto I Energy Center
Other · Callisto I energy center LLC
206 MWOperating Harris, TXERCOT Mar 20212024
Mercury II Solar
Solar + storage · Mercury II Solar, LLC
206 MWOperating Hill, TXERCOT Jan 20212023
Walstrom BESS
Battery storage · Sealy Power LLC
205 MWOperating ERCOT Jul 20212025
Anemoi Energy Storage
Other · Anemoi Energy Storage, LLC
205 MWOperating Hidalgo, TXERCOT Sep 20212024
Corazon Storage
Solar + storage · Guajillo Energy Storage LLC
205 MWOperating Webb, TXERCOT Aug 20212025
Ebony Energy Storage
Other · Ebony Energy Storage, LLC
204 MWOperating Comal, TXERCOT Feb 20212024
Solar project GI-TC-2021-05, Mckinley County
Solar
200 MWOperating Mckinley, NMWest Mar 20212023
Onshore wind project GI-TC-2021-06, Logan County
Onshore wind
200 MWOperating Logan, COWest Mar 20212021
Turquoise Storage
Other · BT Cunningham Storage, LLC
196 MWOperating Hunt, TXERCOT Mar 20212023
Blevins Storage
Battery storage · Blevins Solar, LLC
181 MWOperating Falls, TXERCOT Feb 20212025
Avila BESS
Battery storage · BRP Avila BESS LLC
164 MWOperating ERCOT May 20212025
Hart Wind
Onshore wind · Hart Wind Project LLC
163 MWOperating Castro, TXERCOT Oct 20212025
Wolf Tank Storage
Other · Lobo Storage
156 MWOperating Webb, TXERCOT Jul 20212023
Desert Willow BESS
Battery storage · Desert Willow Energy Storage, LLC
154 MWOperating Ellis, TXERCOT Feb 20212025
Solar project Q30, Maricopa County
Solar
150 MWOperating Maricopa, AZWest Jul 2021target 2023
Solar project CLPT G14, Laramie County
Solar · South Cheyenne Solar, LLC
150 MWOperating Laramie, WYWest May 2021target 2023
Solar project ANPP HVS-Q30
Solar
150 MWOperating West Jul 2021target 2023
Timberwolf BESS 2
Other · Crane 2 BESS, LLC
150 MWOperating Crane, TXERCOT Mar 20212023
Solar project Q30b
Solar
150 MWOperating West Jul 20212023
Sheep Creek Storage
Other · Longhorn Storage LLC
142 MWOperating Callahan, TXERCOT Jul 20212024
Pioneer DJ Wind
Onshore wind · Pioneer Hutt Wind Energy LLC
140 MWOperating Midland, TXERCOT Oct 20212025
Blue Summit I Repower
Wind + storage
135 MWOperating Wilbarger, TXERCOT Oct 20212024
Giga Texas Energy Storage
Other · Giga Texas Energy, LLC.
131 MWOperating Travis, TXERCOT Apr 20212024
Anchor Wind II
Onshore wind
129 MWOperating Eastland, TXERCOT Apr 20212024
Connolly Storage
Other · BT Connolly Storage, LLC
125 MWOperating Wise, TXERCOT Oct 20212024
Great Kiskadee Storage
Battery storage · Great Kiskadee Storage, LLC
103 MWOperating Hidalgo, TXERCOT Jan 20212025
Angelo Storage
Other · Angelo Storage, LLC
103 MWOperating Tom Green, TXERCOT Nov 20212024
St. Gall I Energy Storage
Other · St. Gall Energy Storage I LLC
103 MWOperating Pecos, TXERCOT Apr 20212024
River Bend
Other · Brazos Bend BESS LLC
102 MWOperating Fort Bend, TXERCOT Aug 20212024
St. Gall II Energy Storage
Battery storage · St. Gall Energy Storage LLC
100 MWOperating Pecos, TXERCOT Apr 20212025
Gas project SRP-Q70
Gas
99.0 MWOperating West Mar 2021target 2022
Gas project Q70, Maricopa County
Gas
99.0 MWOperating Maricopa, AZWest Mar 2021target 2022
Gas project SRP-Q71
Gas
99.0 MWOperating West Mar 2021target 2022
Gas project Q71, Pinal County
Gas
99.0 MWOperating Pinal, AZWest Mar 2021target 2022
Coral Storage
Other · Copperhead Solar, LLC
99.0 MWOperating Falls, TXERCOT Feb 20212023
Battery storage project 629, Owyhee County
Battery storage · Idaho Power Company‚ÄîPower Supply
85.0 MWOperating Owyhee, IDWest Dec 20212025
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)