St. Gall II Energy Storage

St. Gall II Energy Storage is a 100 MW battery storage request built and operating in the ERCOT interconnection queue, in Pecos County, Texas.

Queue statusOperating
  1. PlanningQueued Apr 2021 (completed)
  2. ConsentedOct 2024 (completed)
  3. Construction (completed)
  4. OperatingJul 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0525
Grid region
ERCOT (Texas)
Developer
St. Gall Energy Storage LLC
Connection point (POI)
38355 TNLeon Creek 138kV
Location
Pecos County, Texas
Technology
Battery: 100 MW
Total requested
100 MW
Study phase
IA
Queue status
Operational
Entered queue
12 April 2021
Agreement signed
31 October 2024
Proposed online date
September 2025
Came online
July 2025

Location

Marker shows the centre of Pecos County; the queue data does not give exact sites.